Hi Wastl, we have a 70% regulation. Best regards Thorsten


I am not thrilled either.

Because I made the proposal yesterday: The electrician picks up the meter from the municipal utilities on Monday morning and installs it immediately. The municipal utilities are 8 minutes away from here.

Answer: Not possible. The municipal utilities send someone after the installation of the system to check if everything is properly and correctly installed. Only then is a meter provided.

So everything takes longer and the electrician has to drive twice.....

Well......I can't change it.

Best regards
Thorsten
 

Wastl

2016-03-17 07:30:19
  • #2

You forgot about the mafia-like constellations, because:
The meters are no longer even installed by the grid operator themselves, but by a private subcontractor, which had a backlog of several months at the time. Even after multiple calls, the only response was: You will be scheduled eventually,...
What can be done? Nothing,... Complaints to the grid operator brought nothing at all - reverse running of the household meter was banned back then,...
 

toxicmolotof

2016-03-17 08:12:36
  • #3
What scale of photovoltaics are we talking about here? We have that too, but only for systems larger than x kWp.... (x> 10?, uncertain).
 

T21150

2016-03-17 08:15:13
  • #4
Our system has an installation capacity of 6.675 kWp

2.94 kWp east roof
3.74 kWp west roof
 

toxicmolotof

2016-03-17 08:26:22
  • #5
Here the network operator only moves a finger once. And only if the meter receives the [Adessettiket] for the electrician/solar installer.
 

T21150

2016-03-17 08:32:01
  • #6


Yes, I think so too. Typical Velbert. Huge fuss over small things.
 

Similar topics
08.12.2014Smaller photovoltaic system 2 KWp11
04.04.2016Heat pump on separate meter or together with household electricity20
18.11.2016Electrician's invoice after 2.5 years - What are my rights?18
21.02.2018Economic efficiency of a 10-kWp system vs. a 5-kWp system11
30.08.2018Operating data of a 10 kWp system. Exchange of various data15
11.11.2018Temporary power distributor - buy or rent?11
09.05.2020Photovoltaic system: How much kWp is sufficient for a house?81
29.03.2020Commissioning of 9.3 kWp system combined with air-to-water heat pump and controlled residential ventilation10
06.10.2021Photovoltaic system / heat pump, do you have 2 meters?55
14.06.2021Separate meter and electricity tariff for air-to-water heat pump sensible?103
03.07.2021Separate water meter for garden water - How to read the meter21
13.11.2021Requirements for ancillary apartment, wiring, meters, etc.13
30.03.20229.2 kWP system - size of the battery storage?11
30.01.20231483€ per kWp | CanadianSolar 11.48 kWp and SMA inverters47
14.06.2023Heat pump and household electricity all through one meter25
25.09.2023The supplier has incorrect meter numbers in the system - what to do?42
31.10.2023Extra meter for heat flow tariff (heating electricity tariff) yes/no?36
02.10.2024Photovoltaic - Position on the roof and only one meter?10
06.01.2025Is the photovoltaic price okay? 10.2 kWp and 5 kWh storage14
07.01.2025Is a heat pump meter sensible? According to the bill, yes, but is that correct?13

Oben