What is the appropriate loan amount?

  • Erstellt am 2014-01-21 13:54:19

amelie74

2014-01-22 12:39:34
  • #1
Dear construction expert, what exactly must be included in the [Baubeschreibung] or should be??? I am currently making an overview of what is stated in the provided [BB], otherwise I lose track
 

Der Da

2014-01-22 12:56:36
  • #2
In the BB, everything must actually be stated so that you can assume the mentioned price. If no roof is listed in the description, you have not purchased one, and it will be charged afterwards. As far as I know, there are no legal regulations about what a construction company can omit and what not.

A roof is usually included; that was an extreme example... but what is often missing: construction fencing, protective fences, porta potty rental, debris containers, disposal of excavation, additional costs for foundation, often the slab is missing, or the bathrooms are tiled only 1m high, each cm then costs you extra. And so on and so forth... it is simply impossible to tell you everything. The only help here is to compare several offers and hope that they differ.
Number of sockets and light switches is also such a topic; often far too few are offered, and a €50 surcharge is charged.

It is important to inform yourself before signing. No matter how.
If you are unsure about the construction description, there are people who gladly analyze it for money.
Often this saves real money because you avoid a very expensive additional financing.
 

ypg

2014-01-22 13:49:41
  • #3
The construction performance description states, among other things (as Der Da already says), the entire standard that the company installs. Sanitary equipment of brand x; if you don't like it and want something else (accordingly more expensive), that means an additional charge. Additional charge here and additional charge there. It's like with a new car: a car costs 15,000 naked, with a better engine 18,000, + "Elegance" equipment 22,000, plus plastic parts on the body painted in a different color as well as sunglasses holder, driver's seat height adjustment, navigation system, and alarm system, you're at 25,000. Oh yes: in addition, for a house as for a car, freight and transfer costs come. Back to the house: what is not listed in the construction performance description does not exist either. SAT dish, a lot of sockets and outdoor lamp connections in the electrical system, thermostats, fancy toilet seat and bathroom mirror and a 180x80 tub in the sanitary equipment, tile material over 20 €, and and and mostly come in addition. That is why we are surprised by your low house price.
 

ypg

2014-01-22 13:55:06
  • #4
Just hint at who you want to build with so that we can guess
Maybe the construction work description is on the homepage... then one can say more about whether your 184000 could be sufficient
 

amelie74

2014-01-22 22:10:59
  • #5
The provider has its headquarters in Oberleitersbach. We have included the foundation slab in the purchase price. However, floors and painting work must be done by us ourselves. But we have fully tiled all bathrooms and guest toilets (floor, wall) and equipped them with Villeroy and Boch sanitaryware. Underfloor heating throughout the house, roller shutters as well (except on dormer windows, roof windows). Satellite system is not included. Questions regarding the following: debris container, portable toilet, crane positioning, scaffolding, foundation slab included... I haven’t listed everything now – it would be too much.
 

ypg

2014-01-22 23:09:40
  • #6
They seem serious to me, yet there is no open construction service description to be read. I also had a Variant house calculated once - it was an almost finished version (I looked in my emails from back then, it was too expensive for me). Now the interior doors and the plastering work make sense to me with you. Plastering work costs money or - if done yourself - takes time. Two weeks is nothing. Please plan for that! In addition to the time factor, there are the floor coverings and the wallpapers, so you could have a financial double burden for a total of 2-3 months... With this house provider, there are definitely construction diaries - just inquire there about how much they had in additional costs.
 

Similar topics
16.01.2012Single-family house construction description - experiences?10
21.10.2017Experiences with rimless toilets104
15.06.2015Base slab or strip foundations for garage12
24.07.2016Alternatives to the Dixi toilet?14
13.03.2017Construction planning, construction work description, cost breakdown19
18.10.2015First Ikea kitchen... Now with backsplash (p. 7)61
21.10.2017Sealing the base slab before the roof is installed19
27.10.2017Construction description by architects: Who has experience?13
01.12.2017The bank may want a construction service description despite individual subcontract awarding26
01.08.2018Description of construction services - Performance assessment?12
29.10.2018Earthworks in the construction performance description17
07.11.2018Cutting the floor slab due to incorrectly placed drainage pipes20
09.02.2019Ground slab with strip foundation and frost skirt23
23.01.2020Construction work description - Thin slab foundation disadvantageous?11
13.01.2025Insulating wooden floor panel with straw20
11.03.2021Building description for a single-family house with a basement42
11.06.2021Construction performance description from the favorite - Is something missing?65
11.03.2023Plot Single-family house C630 Heinz von Heiden at the location Saxony64
16.03.2023Replace a standard washbasin with a washstand system myself?23
18.03.2025Overview of the offer and construction work description20

Oben