The plot must be developed. The general contractor says this is a priority!

  • Erstellt am 2015-06-02 16:41:15

f-pNo

2015-06-15 16:47:41
  • #1




Next time I'll just leave out the article - then I'll avoid such traps :cool:.
 

Bautraum2015

2015-06-15 16:48:23
  • #2
:D
 

Bauexperte

2015-06-15 18:15:57
  • #3
Then make sure to check how long the fixed price applies under which conditions and above all: submit the building application this year. If not, it will be more expensive for you next year anyway ;) Rhenish greetings
 

ypg

2015-06-15 18:23:35
  • #4
just for your information... has already fixed it.



(the OP) can only start next spring but doesn’t see a problem with that.



is in a bit more of a hurry and after signing in April wants to have moved into the house by November.
 

Payday

2015-06-17 10:54:35
  • #5

No, it is a complete new build (empty plot, but fully developed and registered in land registers, etc.) in solid house construction. No drywall, no wooden walls. Construction started last week, the ground floor is now almost completed. Next Monday the ground floor ceiling will be installed. Our neighbor, who also built with them, had the acceptance inspection the day before yesterday after 4.5 months of construction time (from the first time the excavator rolled in).

Weather conditions can delay the construction, but only the shell until the roof/windows are installed. And that will be done by mid-July. Currently, the sun is shining and it is warm, so delays are unlikely.

We chose the construction company because we want to finish quickly. The shorter the time, the lower the risk of total loss due to bankruptcy and so on. Also, the company is already larger and we trust that they know what they are doing.

We had a building notification prepared, which was confirmed on time with the payment request after 4 weeks.
 

Bauexperte

2015-06-18 13:07:27
  • #6
Hello,


The signature under the construction contract was in April and construction began in week 24 - that means you, or rather your BU, had – assuming you signed in week 16 – a full 8 weeks (minus 5 holidays) for the preparation of the building application and review by the authority according to the simplified approval procedure, soil survey, structural analysis, work planning as well as the creation of execution plans and foundation including civil engineering. Impressive performance!


Prefabricated ceilings and windows currently have long delivery times; the interior work will sensibly only begin once the shell is closed.


Focusing solely on the timeline as the main selection criterion does not seem very confidence-inspiring to me. But I’m sure you will report back ;)

Rhenish regards
 

Similar topics
14.11.2011Shell construction still this year15
13.02.2014Mold on wood/ shell construction, is it possible to deduct the advance payment invoice?28
27.02.2015Purchase shell construction and complete it including financing15
22.02.2016Signature of the work contract before financing?15
07.05.2016Buying a shell construction - Experiences21
31.07.2016Electrical inspection, Q2, bathroom tiles, knee wall, floor-to-ceiling windows23
03.10.2016Single-family house, hillside location, basement half residential/useful area - expensive shell construction?15
03.12.2019Additional costs due to incorrectly planned ventilation system + floor-to-ceiling windows?50
24.06.2017Construction ancillary costs: Bank requires signature from the architect16
30.08.2017Signature of prefabricated house under reservation with right of withdrawal16
11.08.2019Installing raffstores in the shell construction prepared for blinds15
27.10.2019Water in the inner frame: Shoddy construction? (Shell construction)15
24.12.2019Windows are smaller than in the building application/work plan.40
05.04.2021City villa window 1.26x1.45 visual error?10
25.11.2021Getting rid of moisture from the shell construction - how to ventilate and other topics18
29.11.2022Front view windows are suboptimal and need to be optimized90
19.12.2022Separate awarding of windows and shutters - GU resists!34
27.11.2023Assessment of costs for the shell construction and total costs (plaster, screed)17
28.03.2024Offer for shell construction of a single-family house 170 sqm - Is the price market-appropriate?57
24.02.2025Construction Costs Shell/Turnkey Comparison39

Oben