The plot must be developed. The general contractor says this is a priority!

  • Erstellt am 2015-06-02 16:41:15

Bauexperte

2015-06-15 11:23:38
  • #1
I consider that a rumor, unless you are jumping on an ongoing construction project (for example by the BT) ;) Here too, I am sure that exceptions were signed that "can" extend the construction time backwards. Rhenish regards
 

laemat

2015-06-15 12:29:15
  • #2
Why rumor? You just take a provider who doesn't build beyond their means, then it works out. We also have a construction time guarantee of 5 months from the foundation slab. And for the foundation slab there is a deadline of 8 weeks after the building permit approval. Delay due to weather conditions is of course not included.
 

Bautraum2015

2015-06-15 12:36:07
  • #3
5 months for a solid construction? Or a prefab house. I'm rather critical when it comes to solid construction under 6 months... preferably even 9. And just because someone is fully booked, it doesn't mean they are building beyond their means.... they just do it right, I would say
 

ypg

2015-06-15 12:39:54
  • #4
The building authority apparently does not have many applications to process? We expect a processing time of 3 months. That is average.
 

Bautraum2015

2015-06-15 12:41:36
  • #5
With us even 4-5 months. But the construction boom in our area benefits us in a way, our land value and thus equity have more than doubled
 

BastianB

2015-06-15 12:48:51
  • #6
But it can be done differently :-) Not even 2 weeks with us, however in the simplified building permit procedure, there should be significantly less to check.
 

Similar topics
26.10.2012External perimeter insulation floor slab, basement mold risk11
15.07.2014Foundation slab for Danwood bungalow? Company for complete works?11
15.06.2015Base slab or strip foundations for garage12
27.03.2017Backfilling for foundation slab25
17.07.2017Payment plan okay - 13% after the floor slab?21
19.08.2017Water on the base plate12
07.11.2018Cutting the floor slab due to incorrectly placed drainage pipes20
11.03.2019Is the base plate too deep (planned)?30
14.10.2019Dampness in the basement on the floor slab and walls25
01.07.2019KFW 55 - Insulation under the floor slab37
02.02.2020Insulation under the floor slab - Is it sensible? Experiences39
28.10.2019Base plate - reinforcement visible from the side15
17.04.2024The wall is not level on the base plate or protrudes by 2 cm26
23.01.2020Construction work description - Thin slab foundation disadvantageous?11
12.03.2020Start of house construction / Foundation slab is being laid / Tips13
27.06.2020Base plate incorrectly positioned40
14.08.2020Potato cellar - floor slab - construction25
11.01.2021Basement or slab? - Cost estimation24
07.01.2021Recessed entrance in a prefabricated house: with or without a floor slab11
17.02.2021Our slope location - ground slab vs residential basement42

Oben