The plot must be developed. The general contractor says this is a priority!

  • Erstellt am 2015-06-02 16:41:15

Bauexperte

2015-06-15 11:23:38
  • #1
I consider that a rumor, unless you are jumping on an ongoing construction project (for example by the BT) ;) Here too, I am sure that exceptions were signed that "can" extend the construction time backwards. Rhenish regards
 

laemat

2015-06-15 12:29:15
  • #2
Why rumor? You just take a provider who doesn't build beyond their means, then it works out. We also have a construction time guarantee of 5 months from the foundation slab. And for the foundation slab there is a deadline of 8 weeks after the building permit approval. Delay due to weather conditions is of course not included.
 

Bautraum2015

2015-06-15 12:36:07
  • #3
5 months for a solid construction? Or a prefab house. I'm rather critical when it comes to solid construction under 6 months... preferably even 9. And just because someone is fully booked, it doesn't mean they are building beyond their means.... they just do it right, I would say
 

ypg

2015-06-15 12:39:54
  • #4
The building authority apparently does not have many applications to process? We expect a processing time of 3 months. That is average.
 

Bautraum2015

2015-06-15 12:41:36
  • #5
With us even 4-5 months. But the construction boom in our area benefits us in a way, our land value and thus equity have more than doubled
 

BastianB

2015-06-15 12:48:51
  • #6
But it can be done differently :-) Not even 2 weeks with us, however in the simplified building permit procedure, there should be significantly less to check.
 

Similar topics
21.10.2011Floor slab insulation "Yes!" or "No!"14
18.09.2012Construction of a base slab with frost skirt but without foundation10
31.05.2015Wastewater pipe concreted in the floor slab at the wrong location29
14.09.2012House financing - house, garage, and foundation slab approx. 290,000 EUR11
26.10.2012External perimeter insulation floor slab, basement mold risk11
21.11.2013Is the floor slab still possible this year?15
15.07.2014Foundation slab for Danwood bungalow? Company for complete works?11
23.11.2014Stone throw on foundation slab - builder's liability insurance?16
15.06.2015Base slab or strip foundations for garage12
07.09.2015Minimum distance from the base plate?11
11.09.2016Base plate - construction/insulation etc. - experiences please!10
05.08.2016Leave the floor slab over winter15
20.08.2016Base slab vs strip foundation15
13.09.2016Insulation under the floor slab EPS or XPS?12
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
06.10.2016Base plate with defects?22
27.11.2016Double insulation below and above the floor slab?10
22.07.2017Horizontal sealing of the base slab24
20.02.2017Dimensions of the base plate do not match25
27.03.2017Backfilling for foundation slab25

Oben