Nixwill2
2022-10-19 08:12:41
- #1
Hello everyone,
Since July we have had our approved building permit, but since then absolutely nothing has happened on the part of the house builder (prefabricated house). Nothing is being planned until the selection appointment, and we have now received a selection appointment for February ’23.
The original timeline was basement in Dec. ’22, house about 4-6 weeks later, and move-in roughly April-May ’23.
Now we are already being told that the basement will come at the earliest 2-3 months after the selection appointment, the house will not be delivered 4-6 weeks later as originally planned but 5-6 months later, and the finishing work will apparently not take 3-4 months but rather about 6 months.
This means overall so far that it could be a whole year later than originally agreed before we can move in.
We have a construction contract according to the Construction Code. Unfortunately, the contract does not say a word about the delivery date or the move-in date (I know, we were pretty naive and stupid and trusted the sales representative too much).
All this is repeatedly explained by missing materials and delivery problems, although we actually believe that the house builder messed up the orders, took on way too much (before everything completely collapses), and now cannot serve fast enough.
(Of course we are also struggling with the costs and cannot/will not just keep watching. The loss of subsidies hit us pretty hard, then of course the general price increases, from June ’23 we will pay the full loan plus current rent, from November ’23 also default interest at the bank. The kitchen is planned for delivery in May ’23, and there will also be price increases and storage costs for us, and as I said the selection appointment has not even taken place; we don’t even want to know the prices for floor coverings and such.)
What I actually want to know from you is, what is the overall current situation with raw materials? I have lost track and hear here and there that it has basically stabilized. Of course, it’s not like it used to be (order today, arrive tomorrow), but if you plan smartly, you actually get your stuff on time; it’s no longer a surprise that for a house you need insulation in 4 weeks, and it works out.
What can you say about that? Is the delivery situation still that bad out there?
Best regards
Since July we have had our approved building permit, but since then absolutely nothing has happened on the part of the house builder (prefabricated house). Nothing is being planned until the selection appointment, and we have now received a selection appointment for February ’23.
The original timeline was basement in Dec. ’22, house about 4-6 weeks later, and move-in roughly April-May ’23.
Now we are already being told that the basement will come at the earliest 2-3 months after the selection appointment, the house will not be delivered 4-6 weeks later as originally planned but 5-6 months later, and the finishing work will apparently not take 3-4 months but rather about 6 months.
This means overall so far that it could be a whole year later than originally agreed before we can move in.
We have a construction contract according to the Construction Code. Unfortunately, the contract does not say a word about the delivery date or the move-in date (I know, we were pretty naive and stupid and trusted the sales representative too much).
All this is repeatedly explained by missing materials and delivery problems, although we actually believe that the house builder messed up the orders, took on way too much (before everything completely collapses), and now cannot serve fast enough.
(Of course we are also struggling with the costs and cannot/will not just keep watching. The loss of subsidies hit us pretty hard, then of course the general price increases, from June ’23 we will pay the full loan plus current rent, from November ’23 also default interest at the bank. The kitchen is planned for delivery in May ’23, and there will also be price increases and storage costs for us, and as I said the selection appointment has not even taken place; we don’t even want to know the prices for floor coverings and such.)
What I actually want to know from you is, what is the overall current situation with raw materials? I have lost track and hear here and there that it has basically stabilized. Of course, it’s not like it used to be (order today, arrive tomorrow), but if you plan smartly, you actually get your stuff on time; it’s no longer a surprise that for a house you need insulation in 4 weeks, and it works out.
What can you say about that? Is the delivery situation still that bad out there?
Best regards