Subcontract before purchasing the property?

  • Erstellt am 2019-05-09 10:18:07

goalkeeper

2019-05-10 13:22:26
  • #1
EDIT: I just remembered that I could also provide a notarization from the bank - that can be done within one to two weeks time-wise and shows the bank that it can disburse the loan before it is recorded in the land register. That should be much faster then.
 

Lumpi_LE

2019-05-10 13:26:15
  • #2
Bank, property, etc. is not the only risk. When we signed our contract with the shell builder, it was said that it could start at the beginning of November. Then something came up and we were postponed to December, then it was said that it was no longer worth starting before Christmas, then January and February were too cold, and at some point in March it finally got started... It goes like this in 2 out of 3 cases. A commitment from a general contractor is worth just as much.
 

goalkeeper

2019-05-10 13:45:54
  • #3
All right – we will certainly pay our dues. Currently, I simply assume that if the general contractor tells me it will work, we plan accordingly and assume that we are not being lied to. Especially because he has an excellent reputation among customers, suppliers, and building authorities in the region.
 

Lumpi_LE

2019-05-10 13:48:26
  • #4
I don't want to spread fears. I’m keeping my fingers crossed that everything goes well. But there are also people who terminate their rental contract before the ink on the paper is dry and for whom a double financial burden after 12 months threatens their existence. If neither applies to you, you can be completely calm.
 

goalkeeper

2019-05-10 14:03:45
  • #5


I’m actually glad about the various warnings here – with all the impressions and appointments, one sometimes loses sight of what’s important.

However, we live directly with the landlords (flexible termination) – fortunately, this is not a problem. A double financial burden still hurts, of course – whether you can afford it or not. It’s just money wasted unnecessarily.
 

Mottenhausen

2019-05-10 14:32:17
  • #6
I believe that before winter your shell structure in your situation probably won't be sealed anymore, so that the "interior trades" could continue afterwards. That means you will likely have a winter break in between. Construction start in June or July and everything will be fine, no question! But:



The general contractor is only waiting for your signature, he would never say "hmm, well, it might be tight this year" because the risk that you run to a competitor if everything is going to take longer anyway is way too high.

Just a quick note from our experience:

Land purchase --> land registration took over 3 months because the key person there was sick. Isn't there a deputy? Apparently not! I mean, WTF?

But that's all preliminaries; the actual construction start was also not as easy as expected:

We also had a development plan with an exemption instead of a building application, but: the planning went in several phases: tender planning (you have completed that), approval planning for construction notification was somewhat tougher because there were issues like emergency exits vs. electric shutters = additional costs and such stories on the table. Then comes the detailed planning or execution planning, structural engineering, ventilation system planning, drainage plan, roof truss plan and who knows what else. All in iterative loops, since for example the statics required a thicker slab and reinforcements, which slightly affected the floor plan, which in turn changed the statics and so on and so forth. At times it felt somewhat slow to me. Then the surveyor has to do the rough survey/fine survey on call, more time might pass here as well... time that in the ideal process of your general contractor might be a bit tight.
 

Similar topics
29.01.2014City villa floor plan / Feedback on static analysis, arrangement28
22.02.2016Signature of the work contract before financing?15
24.06.2017Construction ancillary costs: Bank requires signature from the architect16
30.08.2017Signature of prefabricated house under reservation with right of withdrawal16
17.11.2017Construction contract - What is regulated only after signing?10
27.03.2018Urge to sign due to price increase normal?50
05.07.2018Final costs only after structural analysis and heat demand calculation?12
18.09.2019Build the garage yourself - Calculate the statics?28
21.10.2019Construction start still this year (November)?14
16.12.2019What is the cost of the structural analysis for a single-family house?24
07.05.2020Statics/Energy Saving Ordinance Is the offer fair?14
04.01.2023Retaining wall 2 m high without static report?10
04.08.2020Surprising price increase just before signing17
26.03.2021Building with different stones than in approval planning and structural analysis12
11.02.2022Signature for the neighbor's construction project27
08.05.2022Buy a building plot now for construction start in 23 / 24?43

Oben