Sewage is leaking - water is running down the basement wall

  • Erstellt am 2016-03-08 18:36:28

Bauexperte

2016-03-09 12:51:58
  • #1
Then the other way round ... What exactly does moving into a new house mean? Did you buy a pre-owned property and have the plumbing trade renewed, have a house built via an architect in individual trade contracts, or buy a new building via a general contractor/developer? Was there a formal acceptance? Basically, all forms have in common that the craftsman owes you 2 years warranty; if you built via a general contractor, the warranty period depends on the contract and what is agreed therein. Under a Construction Code contract, the period is 5 years. So the question arises, who must be the addressee of your complaint about defects. Regardless, the plumbing company has the right to repair one or two times; but it can also decide to redo the work immediately. I do not know whether I should deduce from your text that the plumbing company has already made one or several attempts to fix the damage. Usually, a request for defect rectification is first made verbally or via e-mail; if this does not work, a complaint about defects must be issued and delivered by registered mail with return receipt and deadline setting. As your description reads so far and the craftsman is still not willing to fix the damage, you will have to consult a lawyer. The question of the next step must be clarified. But I am not allowed to provide legal advice, as this is exclusively reserved for advisory professions in Germany! Rhineland greetings
 

huettenwirt

2016-03-09 13:11:11
  • #2
Thanks in advance for the answers.

So, briefly for a better description:
We have newly built a single-family house. We awarded the trades ourselves. No general contractor / developer, etc.

The water installation was completely done by the plumber. We connected the washbasins, etc. ourselves, but nothing on the pipes.

He has looked at it several times now. The first assumption was that the leak comes from the wastewater pipe of a hand washbasin. He filled this pipe with a compound and tried to seal it.
It didn't help.

All communication was oral.

I think I will now send the notice of defects in writing and set a deadline for the rectification.
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
08.10.2014How do you search for a suitable property developer?30
13.06.2015New construction with developer / construction drawing documents23
15.03.2016Developer changes plot size25
10.09.2016Construction financing and contract with the developer24
02.12.2016Plots in Cologne only through developers?54
21.07.2017Buying a terraced house from a developer - contract content?71
05.09.2017Developer or general contractor! Safety?30
17.10.2017Property developer or independent architect26
30.12.2017Take over the insurance from the developer after handover of keys?15
29.05.2018Buying a house from a developer - required documents33
30.08.2019Must developers indicate immense embankment height/costs?12
04.03.2019Client-side while building with a property developer16
10.09.2019Trouble with the property developer, don't know what to do anymore13
06.01.2020House purchase, prefabricated house from the developer with land10
13.07.2020Developer does not want to offset lump-sum damages with installments19
16.05.2021Approach for Initial Contact with Property Developers & Prefabricated Building Suppliers24
16.03.2022Additional construction costs when building a house with a developer88
03.10.2025Floor plan changes for end-terrace house from the developer134
25.12.2023Behavior in case of imminent delay by the property developer48

Oben