Request for advice

  • Erstellt am 2016-08-08 13:27:56

Sebastian79

2016-08-08 14:56:57
  • #1
What is the invoice amount?
 

oggear51

2016-08-08 15:00:08
  • #2
4800€ just for insulation and insulation strips, screed layer wanted 1500€, so a hefty amount
 

Jochen104

2016-08-08 16:08:47
  • #3
We did it ourselves and needed 3 days with three unskilled people. I would also claim that we did it more meticulously than most screed or heating installers. I find two skilled people working for a week quite excessive. Originally, it was planned to be done by the heating installer.
 

Sebastian79

2016-08-08 16:13:13
  • #4
We took a bit over 7 days for 240 sqm - the two of us. We also worked carefully, used very little loose insulation, and did a lot of carving. But I never want to do it again..... However, including screed and insulation, I paid a bit over 6,000... I find that really high for the TE.
 

Donnerknall

2016-08-08 18:07:21
  • #5
It is now rather uncommon for the heating engineer to also design the insulation. It is of course clear that this takes longer. That it naturally requires 1 week is too much. Realistically, 2 to 2.5 days would be more appropriate for a "precise" design.

The question remains, of course, why the architect handed over the design to the heating engineer! From an outsider’s perspective, you had a fixed price with the screed layer and now the insulation design is charged at an hourly rate by the heating engineer. Since the architect told you this and you agreed, the contract is also verbally valid.

The only thing you might still try is to have the work hour records shown/given to you. These should include the date, employee, time, and materials used. They should be signed either by the client (you) or the architect. Whether this is legally binding in case of dispute, I cannot tell you.

Best regards
 

Basti2709

2016-08-09 08:02:13
  • #6
I read a lot in this forum, most of the time the situation is exactly the opposite. The client has agreed on something that was not adhered to and is asking for advice here. 99% of the time the question comes up, "was it documented in writing?...if not, then you probably have to accept it as it is.."

Here the architect has now communicated something verbally and the written side says something else...but here a valid contract still exists...?
 

Similar topics
14.06.2011New building: Which insulation is appropriate?14
10.07.2011Wall construction and insulation for Kfw 70 house, okay?19
28.10.201236 cm Ytong exterior wall, solid construction, mold formation, insulation37
22.09.2012Insulating prefabricated house with additional insulation, DIY, inexpensive styrofoam19
08.11.2012Insulation in the 70s compared to today, modern insulation, heating costs26
20.11.2012General questions about insulation10
14.01.2013Insulation / Vapor Barrier Top Floor Ceiling / Collar Beam, Open Ceiling14
25.06.2013Saddle roof/insulation into the ridge or up to/on the intermediate ceiling?10
01.07.2013Additional insulation in the Ytong basement (36 cm)14
08.08.2015Insulation wooden beam ceiling10
07.04.2014Planning attic conversion in new construction - heating, ventilation, insulation?14
16.09.2014Termination of collaboration with architect - demands excessive fee28
06.12.2018The architect and the client cannot agree on a design22
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
10.11.2020The architect is wrong with the estimates. And now?29
31.03.2021Comparability of costs Architect vs. General Contractor119
25.04.2022Heating Concept Air-Water Heat Pump Single-Family House 2 Persons - Offer from Heating Technician?15
04.10.2022Architect does not keep the schedule - what to do?21
16.12.2022Forgot insulation on the dormer wall - mold on wood - what to do?13
18.04.2025The living space is approximately 8 m² smaller in the application drawings compared to the draft (GU).89

Oben