Process of house handover and final touches

  • Erstellt am 2017-10-03 02:00:02

Nordlys

2017-10-04 08:29:58
  • #1
Specht GmbH, Bisdorf, Fehmarn.
 

Bieber0815

2017-10-04 23:02:33
  • #2
- You can order a telephone connection immediately, specify your preferred date. In the worst case, you pay already even though you cannot use it yet. That is a minor annoyance. Alternatively: Possibly move in and do without telephone (and internet?) for a while. You have to discuss that with your roommates :P. - Canceling the apartment: Three months’ notice at the end of the month. No risk, no fun. - Acceptance, final payment. It depends! What kind of contract do you have? Purchase contract or contract for work and services? What does the contract say? Very important: Acceptance only with reservation of still outstanding defects. This reservation must go into the protocol. In case of severe defects (only then) you can refuse acceptance. Moving in ("taking possession") is practically considered acceptance. So, acceptance with protocol, then moving in. - In my opinion, Nordlys is only a limited role model. There are certainly contractors who you cannot rely on a handshake with (I do not mean Nordlys here, but contractors in general), but only on written agreements. Since you never know beforehand what to expect and at the same time building a house is usually a life project (with existential risks), it is therefore advisable to play it safe. With the second house with a proven company, then everything can gladly be done by handshake.
 

Nordlys

2017-10-05 09:21:24
  • #3
I want to point out again that at the final inspection it can actually only be about small cosmetic nitpicks as defects, because if you pay attention during construction, the defects should already be noticed in the creation stage, such as wrong window cutout, or poorly pointed brickwork, or asymmetrical roof covering, or so on. Then complain immediately. And insist on rectification, otherwise withhold the partial payment. At the inspection the house is finished, it is practically already accepted in its components through the partial payments, and what is one supposed to change now with serious defects, for example in the masonry, forgotten sockets, etc. Karsten
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.03.2021Withholding payment for defects in the shell construction74
09.05.2021Price adjustment clause in the contract with the general contractor18
03.10.2022Building acceptance of new construction despite missing heat pump. Significant defects?50
19.04.2024Bank withdraws financing commitment due to defects20

Oben