WilderSueden
2023-01-31 22:27:19
- #1
And your acquaintance probably doesn't want to come by just for the process on one day...
If it were only the process. That is needed before the sloped screed. A few days later, however, the actual channel must also be installed so that the tiler can finish working. And mine had to come by again in the meantime to install some extensions for the fittings before it was finally sealed. The expert noticed that this wouldn't work ;)