Good morning everyone,
we have finally found a condominium that is suitable for us, after coming to the conclusion that it is nearly impossible for us to build a house. Now I have a few questions and I hope you can help me.
1. "Contract structure":
There is a developer who has commissioned an architect to build a multi-family house with 6 residential units on her property with separate trade contracts.
The developer has also appointed a "real estate agent" to sell the newly created apartments. We are in contact with this man. He is also a building surveyor and financing broker.
Is this kind of arrangement common?
2. Process:
We spoke with the real estate agent and found him basically trustworthy; we asked many questions and he answered everything well. He said we would have to give him a purchase commitment, then he would reserve the apartment for us and prepare the contracts. Afterwards, the appointment at the notary. A withdrawal before the notary appointment would cost a few hundred euros because of the costs for preparing the contract documents.
Is this normal?
3. Construction description:
This point unsettles me the most. Since we initially wanted to build a house, I have read some construction descriptions of prefabricated houses, which were in part very detailed. This one is quite roughly designed.
For example, it says "Construction of an Effizienzhaus 40+ basement made of precast concrete parts, ground floor/upper floor in solid construction," but details such as data for soundproofing or thermal insulation are not included. Likewise, technical data for the air-to-air heat pump or the decentralized ventilation system. I will write down a few points as examples (if relevant, I can also provide it in full):
He said that nothing is written about the values of the walls, windows, etc., because it meets the requirements of the Kfw 40+ standard and is built accordingly. Regarding the technical equipment, I wanted to know the manufacturer/model, but he said that is not specified more precisely either because the manufacturer might no longer exist at time X or the model may no longer be produced.
What do you think about this? Do you have any helpful tips for us? What should we pay attention to?
we have finally found a condominium that is suitable for us, after coming to the conclusion that it is nearly impossible for us to build a house. Now I have a few questions and I hope you can help me.
1. "Contract structure":
There is a developer who has commissioned an architect to build a multi-family house with 6 residential units on her property with separate trade contracts.
The developer has also appointed a "real estate agent" to sell the newly created apartments. We are in contact with this man. He is also a building surveyor and financing broker.
Is this kind of arrangement common?
2. Process:
We spoke with the real estate agent and found him basically trustworthy; we asked many questions and he answered everything well. He said we would have to give him a purchase commitment, then he would reserve the apartment for us and prepare the contracts. Afterwards, the appointment at the notary. A withdrawal before the notary appointment would cost a few hundred euros because of the costs for preparing the contract documents.
Is this normal?
3. Construction description:
This point unsettles me the most. Since we initially wanted to build a house, I have read some construction descriptions of prefabricated houses, which were in part very detailed. This one is quite roughly designed.
For example, it says "Construction of an Effizienzhaus 40+ basement made of precast concrete parts, ground floor/upper floor in solid construction," but details such as data for soundproofing or thermal insulation are not included. Likewise, technical data for the air-to-air heat pump or the decentralized ventilation system. I will write down a few points as examples (if relevant, I can also provide it in full):
[*]Base plate: gravel layer, 25 cm concrete slab, stainless steel ring earth electrode, drainage pipes KG2000 DN100, PE foil under foundation slab, continuous perimeter insulation
[*]Basement: exterior wall prefabricated two-shell elements with in-situ concrete core, waterproofing, 120 mm perimeter insulation, dimpled membrane with fleece. Interior wall 12 cm precast concrete parts
[*]Ceiling above basement, ground floor, upper floor: reinforced concrete ceiling
[*]Stairs: concrete stairs, covering "rosa beta"
[*]Elevator
[*]Ground floor/upper floor: exterior walls: masonry wall 36.5 cm insulated, lime plaster interior paint, silicate plaster exterior paint. Interior walls Olanz brick 24 cm, 11.5 cm, lime plaster white paint.
[*]Windows: plastic window systems triple glazing with warm edge according to DIN EN673, number/size see plan
[*]Front door: aluminum main entrance door
[*]Heating: air-to-air heat pump, underfloor heating
[*]Ventilation: decentralized
[*]Photovoltaic system: generation including power storage 6.5 kWp, 6.5 kWh
[*]Sanitary: UP support for washbasin + WC, HT pipes as wastewater pipes, cold/hot water pipes made of plastic composite material, bathroom fixtures see plan, execution program Clivia.
[*]Interior finishing: window sills artificial stone, tiles and floor coverings €80/sqm including labor, interior doors hollow core, apartment entrance doors fire-resistant doors.
He said that nothing is written about the values of the walls, windows, etc., because it meets the requirements of the Kfw 40+ standard and is built accordingly. Regarding the technical equipment, I wanted to know the manufacturer/model, but he said that is not specified more precisely either because the manufacturer might no longer exist at time X or the model may no longer be produced.
What do you think about this? Do you have any helpful tips for us? What should we pay attention to?