Looking for developers in SH - experiences

  • Erstellt am 2021-01-25 23:32:02

Nölting

2022-05-06 18:05:19
  • #1
We are currently building with Kagebau and feel completely cheated. The drama began immediately after signing the contract. First, we were informed that construction would start in late summer instead of spring. Then we were confronted with significant additional costs (earthworks, shoring, drainage, costs for a safety and health coordinator, etc.) despite a fixed price. No verifiable statics were submitted to the structural engineer. Subsequently, the reinforcement plans were not submitted. Construction finally began in spring one year later. After the completion of the basement, no further verifiable documents were submitted to the structural engineer, resulting in a 6-month construction delay. After one year of construction, the shell is only about 30% complete. Over the winter, the shell was left unprotected. We eventually had to pump 40 cm of water out of the basement. The construction site looks like a battlefield. Actually, it is a construction ruin. Currently, the construction project is 5 months behind schedule. This does not interest Kagebau at all. They see absolutely no fault on their part. There is no construction planning. Kagebau openly threatens not to continue construction if the presented interim payments are not made despite defects in the building and a contractually agreed penalty. The general contractor contract is only binding for the client anyway. Otherwise, Kagebau does not care about the contract. They act according to might makes right. After 28 months of construction, the project is on the brink of collapse. We will terminate the construction contract with Kagebau for special reasons. It is a disaster. We strongly advise against this construction company.
 

Neubau2022

2022-05-06 18:15:39
  • #2


A stupid question that I ask everyone: Where was the external construction supervisor? Didn’t you hire one? They might have been able to act differently than you.
 

11ant

2022-05-06 19:37:21
  • #3
As likeable (and in principle also as loud as possible singable) as I find your litany about the construction supervisor: he can only critically assess what (and how something) has been done – not what is still postponed to be done. Besides his technical competence, he has nothing (to offer): he has no authority, let alone that of a judge. He cannot force anyone to finally get moving. Thus, he remains "merely" a knowledgeable support for the party "client," but without means to exert any pressure so that his findings lead to required actions by the building contracting partner.
 

Neubau2022

2022-05-06 19:50:01
  • #4


However, he can give many helpful tips from his experience and possibly talk to the construction manager differently than the client would. I think he would have been helpful in this case as well.
 

Nida35a

2022-05-06 21:13:52
  • #5
The external construction supervisor can certainly notice and announce when the lawyer should be called in because the construction company is fooling and cheating the client. Clients alone hope until ruin.
 

Similar topics
14.01.2013Problems with construction company. Need urgent help!!!17
14.11.2011Shell construction still this year15
05.09.2015Cracks in masonry (shell construction)14
27.07.2013Average construction time for a semi-detached house with a basement11
13.02.2014Mold on wood/ shell construction, is it possible to deduct the advance payment invoice?28
24.04.2015Buy tiles during shell construction24
09.03.2015Received an offer from a builder: Cost of shell construction - experiences?26
27.02.2015Purchase shell construction and complete it including financing15
18.03.2015Developer information varies. What is the realistic construction time?19
11.02.2016Cost per cubic meter of built-up shell space14
19.01.2016Is a home construction project realistic?22
02.06.2016Necessary insurances during construction and afterwards11
29.06.2016Brandenburg Building Regulations / July 1, 2016 - Structural verification engineer no longer required11
23.01.2017What to do if the construction time is not met15
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
17.02.2020Construction companies from Schleswig-Holstein37
28.10.2019Received an offer for my shell construction18
09.07.2021Is the construction time specified in the prefabricated house contract binding?19
28.10.2021External construction supervisors Berlin / Brandenburg towards West24
06.06.2023Estimation of construction time for the new build of a semi-detached house17

Oben