LastCookie
2023-10-11 15:24:05
- #1
To me, this sounds overall like a disguised general contractor (GC) and a construction contract with architectural services (and thus rather not an architect’s contract with the corresponding professional liability insurance).
Here I do not understand the sequence of events: the building authority has to impose conditions already in the permit, construction may only begin after approval, so I do not understand the "follow-up" afterward; the separation (on which side, by the way, the ridge beam* is here practically "shared"?) should have been implemented before the roofing.
*) Your semi-detached house is somewhat atypical in that the halves meet at the ridge, see
The architect must also observe the fulfillment of fire protection regulations taking into account the aforementioned particularity and must anticipate the condition for the building permit. There are no "additional costs" in the sense of the construction contract, as compliance with building regulations and the resulting requirements are, even without separate mentions in the construction specifications or the like, of course part of the construction contract and thus also of any flat-rate price. The GC simply miscalculated here. The architect "made a mistake," but the building authority reacted appropriately by issuing the permit with the condition instead of rejecting it due to the unmet fire protection regulations. The architect should have already included the separation in the plan, and for the GC it was an integral part of the agreed work. Most semi-detached houses have halves adjoining at the gable side; presumably, the GC here built a transverse twin for the first time ;-)
Hey, thanks a lot first of all for your detailed answer. I interpret this as meaning that the whole thing could be booked under "entrepreneurial risk"? I find it somewhat cheeky that the GC here tries to exploit the customers' ignorance. He has done this several times before, but the situation is different now. The house is finished, we live in it, and still have money owed to him (because we haven’t done final acceptance yet, among other reasons because the fire protection and roof issues are still far from resolved).
Even though I could sit this out to a certain extent (he also doesn’t budge on the outstanding amount, which is five-figure), I still want the work to be completed and the house to be accepted by the authority.
For understanding, here is a brief summary:
- We had a permit from the authority with the original architect’s plans, which, however, did not show the separation of the houses in the fine details
- It only became apparent during a spontaneous shell acceptance (the inspector came by bike)
- I also told the gentleman why the authority issued a building permit and hadn’t noticed this before or communicated any conditions... I can’t remember the exact wording anymore. It goes without saying, the architect should do his homework, etc.
I have attached the architect’s solution, which was approved by the authority. Now someone just has to do it.
Regarding the semi-detached house itself, it does offer us some advantages that the ridge runs like this and not differently (I’m missing the technical term here)... we were able to install floor-to-ceiling windows in every room upstairs. And the roof slopes only begin at 1.55 m – otherwise, we would have roof slopes and thus only skylights in the rooms upstairs.
The fire protection issue is totally annoying, and ideally, I would like to come to some agreement, but I think he will stick to his opinion, and in the end, a lawyer will have to settle it.