AMNE3IA
2020-10-25 19:55:51
- #1
Hello
In my house, I have laid 4,500 meters of cables (electricity, alarm system, telephone, etc.) myself. I chased all the slots myself, laid a lot under the suspended ceiling, installed empty conduits in the cellar ceiling and pulled cables through them. I worked on it after work and on weekends for 3 months (not completely, I also did other things during that time). For example, in my hobby room, I have 64 sockets, one outlet and a switch for three-phase power. I planned everything myself. I actually know better where I need what kind of electric installation than the electrician.
OK, you need to have a master electrician who cooperates. But it saves a lot.
Steven
I also did almost everything myself and pulled about 4.5 km of cables in total.
Planning and effort are not to be underestimated. Like Steven, I took about 3 months.
You should have an electrician on hand who can answer ongoing questions,
otherwise it gets difficult. You definitely save a lot. But I would do it again anytime,
because during this time you constantly get more ideas that you implement continuously.
The general sequence was roughly as follows:
1. Planning phase.
The most important phase ever!
The furniture must be drawn into the finished floor plan, and only then do you plan sockets, lighting, network, etc.
Simply putting a double socket in every corner is not, in my opinion, the right approach.
Of course, to be safe, you can put a double socket here and there.
But I find that most sockets should be positioned very individually.
Even the electrician cannot help with that.
I measured and labeled every socket, switch, light outlet, etc. in the floor plan and printed it out for the construction site. Nevertheless, I made some corrections on site here and there.
2. Created a material list for the entire electrical installation (cables, switches, network cabinet, control cabinet (and corresponding components), satellite system, etc. Basically the complete electrical installation.
Here I had support from my electrician. Otherwise, I would have been lost.
3. Requested quotes from several online vendors.
Even here, price differences of up to 30% occurred.
4. Marked the ground floor.
5. Cut out openings for sockets, chased the slots, chiseled and drilled holes.
6. - Pulled cables over the filigree ceiling for the ground floor
- Pulled cables over the filigree ceiling for outdoor lighting, awning control, network, etc.
- For the outdoors from the ground floor only for a few sockets we forgot and for the garden house.
7. Installed flush-mounted boxes and fixed cables.
After that, there was a break until the upper floor was finished being built.
8. The same procedure as on the ground floor, only the cables had to be routed over the floor and ceiling.
The workload was actually less but still more time-consuming because the cables had to be pulled and fastened at the floor and ceiling.
8.1. Attic done in parallel with the upper floor (sockets, lighting, satellite, network, solar, etc.)
Small tip on the side: As long as the exterior scaffolding is still up, I would possibly mount, e.g., the satellite dish and align it with a sat finder, install a weather station if it is located on the roof, set up cameras or install under eaves lighting.
9. Pulled cables for the double garage and workshop (which was only finished being built and roofed later)
Currently, our walls are freshly plastered.
The next tasks are to install and wire the control cabinet and network cabinet (this will be done by my electrician.
Of course, I won’t be there for that).
Install and wire sockets, switches, etc.
I hope I could help a bit