Lay electrical wiring yourself?

  • Erstellt am 2020-10-23 10:46:18

AMNE3IA

2020-10-25 19:55:51
  • #1

I also did almost everything myself and pulled about 4.5 km of cables in total.
Planning and effort are not to be underestimated. Like Steven, I took about 3 months.
You should have an electrician on hand who can answer ongoing questions,
otherwise it gets difficult. You definitely save a lot. But I would do it again anytime,
because during this time you constantly get more ideas that you implement continuously.

The general sequence was roughly as follows:
1. Planning phase.
The most important phase ever!
The furniture must be drawn into the finished floor plan, and only then do you plan sockets, lighting, network, etc.
Simply putting a double socket in every corner is not, in my opinion, the right approach.
Of course, to be safe, you can put a double socket here and there.
But I find that most sockets should be positioned very individually.
Even the electrician cannot help with that.
I measured and labeled every socket, switch, light outlet, etc. in the floor plan and printed it out for the construction site. Nevertheless, I made some corrections on site here and there.

2. Created a material list for the entire electrical installation (cables, switches, network cabinet, control cabinet (and corresponding components), satellite system, etc. Basically the complete electrical installation.
Here I had support from my electrician. Otherwise, I would have been lost.

3. Requested quotes from several online vendors.
Even here, price differences of up to 30% occurred.

4. Marked the ground floor.

5. Cut out openings for sockets, chased the slots, chiseled and drilled holes.

6. - Pulled cables over the filigree ceiling for the ground floor
- Pulled cables over the filigree ceiling for outdoor lighting, awning control, network, etc.
- For the outdoors from the ground floor only for a few sockets we forgot and for the garden house.

7. Installed flush-mounted boxes and fixed cables.

After that, there was a break until the upper floor was finished being built.

8. The same procedure as on the ground floor, only the cables had to be routed over the floor and ceiling.
The workload was actually less but still more time-consuming because the cables had to be pulled and fastened at the floor and ceiling.

8.1. Attic done in parallel with the upper floor (sockets, lighting, satellite, network, solar, etc.)
Small tip on the side: As long as the exterior scaffolding is still up, I would possibly mount, e.g., the satellite dish and align it with a sat finder, install a weather station if it is located on the roof, set up cameras or install under eaves lighting.

9. Pulled cables for the double garage and workshop (which was only finished being built and roofed later)

Currently, our walls are freshly plastered.
The next tasks are to install and wire the control cabinet and network cabinet (this will be done by my electrician.
Of course, I won’t be there for that).
Install and wire sockets, switches, etc.

I hope I could help a bit
 

Christian144

2020-10-26 12:15:40
  • #2


Thanks for the detailed description. - Can you estimate how much time you needed for the preparations, i.e., for chiseling the wall cutouts? - How big is your house? - Did you approach the electrician directly and explain what you were planning, or how did you find your electrician?

Regards and thanks again
 

AMNE3IA

2020-10-26 12:25:33
  • #3
- Once everything is marked, one working day per floor should be enough (maximum 2 days). Maybe a bit more on the ground floor. Marking took me longer, depending on how picky you are and what kind of stone you have. - The house is 190 sqm in size - A very good friend of mine is a master electrician. He supported me.
 

Steven

2020-10-26 13:16:28
  • #4
Hello Christian Borrow or buy a wall chaser and two good diamond blades for sure. Whether to borrow or buy depends on how much time you have. If you can only chisel slots sporadically, it would be advisable to buy a (good) branded wall chaser. Afterwards, you can sell it again quite well. Steven
 

Christian144

2020-10-26 13:51:03
  • #5
I only asked because we will be using timber frame construction and therefore the chasing as preparation will be omitted and the "only" execution in the walls has to be carried out.
 

Similar topics
06.09.2017General: Network, TV line, bus system56
16.07.2015Cable for outdoor lamp too short11
24.12.2015Electrical planning - sockets88
13.04.2016Electrical planning: Where to install sockets, LED and LAN outlets?19
21.03.2019How many power outlets are behind the TV?78
20.02.2017Sockets or power strips19
15.08.2017Sockets directly under light switches? Pros, cons?17
12.09.2019Electricity in garage: fuse box, circuit, sockets21
18.02.2020What height should the sockets be on the TV wall?11
04.08.2019Sockets: Always prepare sets of 5? What is the best way?25
20.02.2020What does the electrician do during the shell construction phase?19
04.02.2020Installation of additional insulation for underfloor heating - cables lie on the raw floor slab25
23.03.2020Building law: Electrician refuses to continue78
19.06.2020Is an extra circuit / residual current device really necessary for the office?40
18.09.2020CAT cable in the utility room - not crimped?45
12.02.2021Retrofitting FI switches, older electronics18
15.01.2022Floor plan planning semi-detached house, ground floor assessment20
27.12.2022Wiring sockets, switches30
09.07.2023Electrician Cost Estimate - New Installation22

Oben