Expired fixed price guarantee - additional costs

  • Erstellt am 2021-05-20 19:20:44

ypg

2021-05-20 23:16:25
  • #1
The question is of course addressed to you. In the calculation for financing, a buffer for unforeseen circumstances is always included. 10-20%. That should cover the scenario; the rest must be saved somewhere. I really do not want to be in your shoes – it is certainly very unsatisfactory. Nevertheless, there must be a Plan B for you.
 

Nida35a

2021-05-20 23:19:28
  • #2

you planned a house
+ Muster
+ Garage
+ Terrace
+ Paths, driveway
+ Fence system,
consider which of these plus signs can be postponed by months/years,
and the order.
There should be some leeway for your financing
 

thoughtless86

2021-05-20 23:48:35
  • #3

I’ve planned about 15k for special expenses, with 2% discount on the individual trades more towards 20k. So really as a pure buffer for what still arises during the construction phase, e.g. for a bit more paving/terrace area and for example fence or garden construction. As I said, the rest is completely part of my contract, but I have to say that I’m building with a smaller regional general contractor, the company itself carried out all the civil engineering work and the carpenters and co employed there also do the outdoor facilities etc., which probably makes it easier to plan. For the interior finishing, my contractor organizes the trades himself and thus earns the margin. But I’m optimistic that everything will work out like this. But I also still have reserves in case something really unforeseen happens or a relevant delay occurs. So not planned down to the last euro, I think the current situation quickly becomes dangerous otherwise...
 

Dali2020

2021-05-21 06:38:00
  • #4
We signed our contract last week.

It said that if the construction company does not start construction within 6 months, they are entitled to increase the price by 0.XX% per month. After 12 months, a price adjustment can be made.
Our company extended the first deadline from 6 to 9 months upon request, since it is already foreseeable that the shell construction probably cannot be completed this year.

What exactly does the contract say?
If it is formulated similarly, the 10,000 euros could indeed be correct.
 

Thomas911

2021-05-21 07:17:39
  • #5
Unfortunately, there is no percentage given in our contract. Only that the fixed price guarantee applies until completion if the following points are met within 6 months from the conclusion of the contract: - Building application is approved - Utilities are installed - Construction road is in place
 

Schimi1791

2021-05-21 07:57:46
  • #6

The "stupid" thing is, a few percent more quickly results in five-figure sums in the (house) final price. For that, a grandma has to "knit" for a long time. Just imagine if the price increases were like those for smaller consumer goods. There I have already noticed that prices tend to go up by 15% to 20% by reducing the package contents.


Or reconsider the floor plan/specifications?


Fingers crossed!
 

Similar topics
23.03.2009Does the capital provide financing10
16.06.2011Conclude a construction contract under reservation?10
07.07.2011Financing land now, house in 6 months?17
25.07.2013Is financing possible?10
31.05.2012Financing of the property: Does the entire financing need to be secured?11
22.10.2014When to finalize the financing??15
18.12.2015Financing unequal equity ratios of unmarried partners24
23.08.2015Construction financing with a fixed-term contract13
22.02.2016Signature of the work contract before financing?15
01.05.2016Process of property purchase/financing11
10.09.2016Construction financing and contract with the developer24
14.12.2016House planning, offer, financing, fixed price19
26.02.2017Financing approved by the bank. Better house on offer.28
02.07.2019Financing with a 35-year fixed interest rate52
19.10.2018Job offer but temporary - what options are there for financing21
23.02.2019Only from BHW financing, how can that be???35
12.06.2019Fixed-term employment contract financing?48
13.03.2021Construction start September 2021 - When to take care of financing?21
30.03.2022Terminate the contract with the general contractor "early"22
19.08.2022Fix financing early – no room for negotiation with the home builder?18

Oben