Execution plans changed without consultation!!

  • Erstellt am 2021-10-27 17:20:24

Climbee

2021-11-10 10:15:46
  • #1
: I can understand that you are emotionally involved, but could your posts be a bit less "loud"? Maybe a period instead of ending every sentence with an exclamation mark? I always feel like I'm being shouted at ;)

What surprises me is that the roof is already on, and now you notice that something different was built in the basement. Are you so far away from the construction site that you can't check it daily or at least regularly?
In that case, an independent construction supervisor would have been important to me from the start. But the horse has already left the barn.
Anyway, it's good that you have now involved an expert! It seems like a lot is coming together.
I keep my fingers crossed that your construction won't be significantly delayed and your move-in date won't be jeopardized.
 

Tom1978

2021-11-10 10:24:14
  • #2


External construction supervisors are not important, they are mandatory on every construction site where the client is not a professional.

I am reading along with interest. Keeping my fingers crossed that everything can be rectified.
 

11ant

2021-11-10 10:38:49
  • #3
You surely meant to say: "... are not (only) important,"
 

DaniMartinez

2021-11-12 23:01:17
  • #4
Excuse my spelling! I only actually noticed it when it said timber frame construction ‍♂ … but the planning office admitted the mistake of having changed the plans without consultation.

Unfortunately, there is now the much bigger problem with the shed roof connection. According to the expert, it is defective and urgently needs to be secured! The roof has been on for several weeks already and my site manager approved it as fine! Even the carpenter said at the first contact that it was structurally okay.
I’m attaching the pictures. The gaps between the rafters and the beam are at least 2cm in every case. And for two out of five, which I could check without problems, the nails were hammered in as shown in the pictures. What do you say?


 

ypg

2021-11-12 23:36:51
  • #5
What does your independent construction supervisor say?
 

11ant

2021-11-13 00:15:50
  • #6
We had a similar botch just a few days ago:
 

Similar topics
25.05.2015Extractor hood / roof or wall14
03.03.2015Insulating the roof with kitchen paper/toilet paper12
24.05.2015KfW 55 with wooden house - U-values: Wall 0.18 - Roof 0.1617
05.05.2016Insulate the roof: flakes, panels or wool17
07.03.2020Children's room on the upper floor open up to the roof25
20.09.2016Extending walls beyond the roof?!43
10.03.2017Roof design / Use of 2nd floor mandatory with 2 full floors23
20.10.2017Roof with photovoltaic or other investment, any experiences?19
12.09.2017Roof constructed too flat - Construction company does not acknowledge the defect12
21.10.2017Sealing the base slab before the roof is installed19
20.04.2018Roof covered with fake tiles - house accepted.12
29.10.2018Roof, flat roof, gable roof, shed roof - How much does each cost?22
25.03.2019Ceiling suddenly too small for controlled residential ventilation!54
02.07.2019Purlin distance from exterior wall or roof16
02.12.2019Single-family house (2 floors + residential basement + developed attic) approximately 200 sqm - changes162
07.12.2019Bank guarantee from the roofer due to defects in the roof16
27.02.2020Is the vapor barrier in the roof vapor-permeable? Yes? No!16
10.04.2020Rainwater from the roof - drainage in the soil for discharge?12
14.02.2021Re-roofing, roof tiles not possible45
28.10.2021External construction supervisors Berlin / Brandenburg towards West24

Oben