Since the others are so "mean" ... attached is a kind of orientation aid. Unfortunately, you can't attach Excel files here.
As some have mentioned, the costs are always somewhat individual per construction project, region, location, etc.
Therefore, I simply think start and compile as well as possible. As always, better to have some plan than none at all.
Land & Ancillary Land Costs: 0 |
Land Price |
Notary Fees (1.5%) |
Property Transfer Tax (5%) (Possibly less, as not everything is applied to the total amount) |
Land Register Entry & Mortgage Registration (approx. 1% of land value) |
Additional Costs (Construction cost subsidy for granny flat) |
Construction Costs House & Carport & Bicycle Shed: 0 |
Costs House with Ground Slab by General Contractor |
Carport & Bicycle Shed |
Connection Electricity & Wastewater Bicycle Shed |
Greening Carport |
Underfloor Heating Ground Floor |
Prepare Attic as Expansion Reserve incl. insulation of floor ceiling, lay underfloor heating, screed |
Painting Work Ground Floor + Material (Filling, Plaster and Painting) |
Vinyl Floor Coverings Installed |
Base Plaster |
Miscellaneous for the House: 0 |
Secondary Device District Heating & Buffer Tank |
Controlled Residential Ventilation |
Electric Roller Shutters |
Terrace Foundation made of Concrete |
Paving Yard with Material |
Excavation Yard |
Shower built and floor-level |
Heated Towel Rail |
Grille French Balcony |
House Entrance Landing |
Storage Compartment in Shower and Bathtub |
Additional Closed Risers Stair Attic |
|
Material Own Work: 0 |
Material Costs Own Work Attic Insulation (Drywall, Insulation Wool, Battens, Foil) |
Floor Coverings and Rolled Plaster/Wallpaper/Paint Attic (Self-installed & Laminate) |
|
Additional Construction Costs: 0 |
Building Application / Building Permit |
Surveying (Buddy is Surveyor) |
Building Survey after Completion |
Soil Report |
Additional Earthworks (Excavation, Gravel etc.) |
If applicable, Structural Engineer (only in earthquake zones and certain federal states – probably not for us) |
Homeowner Protection Association Membership |
Building Expert |
Construction Fence (Possibly not necessary due to ground slab) |
Building Notification |
Road Closure |
Buffer Additional Construction Site Setup |
Construction Toilet |
Connection Costs for Construction Power Meter Box |
Connection Costs for Construction Water |
Consumption Construction Electricity & Screed Drying |
Heating Costs during Winter before Occupation (possibly) |
Consumption Construction Water |
House Connection District Heating |
House Connection Electricity |
House Connection Water |
House Connection Telephone |
Waste Disposal (Container) |
Topping-out Ceremony |
Connection of House Lines to Shafts (since only 1m outside house included) |
|
After Construction: 0 |
Outdoor Facilities, Outdoor Paths (except Yard) and Garden (material only, since own work) |
Blower Door Test |
Mailbox |
Outdoor Lights |
Terrace Slabs and Material (self-installed on concrete foundation) |
|
|
Interior Finish: 0 |
Kitchen |
Fly Screens for Ventilation Windows |
Furniture (only the necessary since existing ones will be brought along) |
Awning |
Wardrobe & Waiting Bench |
House Lights |
Bar Stools |
Electrical Components (KNX, Loxone, Ubiquity etc.) |
Finance: 0 |
Homeowner Liability Insurance |
Construction Performance Insurance (possibly provided by provider) |
Construction Financing Costs |
Mortgage on Apartment |
Miscellaneous: 0 |
Sample Reserve / Buffer / Unplanned |
City Subsidy |
Moving Costs |
Discount (Terrace, Spray Plaster) |
Total Sum: |