JoachimG.
2020-11-21 14:19:05
- #1
We are currently having an offer prepared for 50m of path including wastewater, surface water, and a complete heavy-duty construction as a construction road and then a fine layer, so that it becomes a clean road to the house. Path: spoke with 2-3 construction companies. One was interested and came for the measurement (channel depths, cover heights, slopes, surfaces, etc.) - Without measurement and exact estimation of depths (channel construction in open trench or with shoring in the shaft, etc.) no one will be able to give you a reliable figure.