Deficient construction management - expert confirmed this

  • Erstellt am 2017-11-17 09:08:47

Jetset

2017-11-17 09:08:47
  • #1
Hello,

we already started building in October 2016. Since my partner and I both work full-time and the planned construction site was about a half hour drive from our old apartment, we commissioned our architect with the construction management.
He assigned an employee to lead his projects.
From the beginning, we were not particularly satisfied because the flow of information was insufficient and we only received answers after multiple inquiries.
Even before the shell construction was completed, the appointed site manager was dismissed and the architect took over personally.
Our hope that this would accelerate the work and that we would be better informed was unfortunately not fulfilled.
Quite the opposite. The architect visited the construction site at most once a week and was hard to reach.
Agreed appointments with the trades were rarely kept. It usually went like this: on Mondays, he briefly stopped by the construction site and then called us to inform us that certain work was to be done on Tuesday. When we then came over the weekend, we usually found that nothing had happened. When we called the architect, he was usually surprised. In my opinion, he almost never had an overview of what was going on at the site and what the current status was.
More or less with the motto... it will be finished eventually...
We had just gotten the screed when two days later rainwater came into the basement through openings in the basement wall for the heat pump connection. The architect knew about these and had roughly stuffed them with glass wool a week before... which of course did 0 good.
After the basement had to be dried out, he said it was no problem. Our construction insurance would pay for it... besides, we lost another 5 weeks because of this, which certainly could have been shortened.
I was at the construction site several times a week after all these incidents and almost every time I had to find out that the drying devices were not running because the fuse had tripped at the construction power distribution box. So they didn't run half the time. Of course, this was reported without result.
The worst was the painting company. One German and four Romanians. The matters were discussed on site with the German, but the employees who came never spoke a word of German and were unable to coordinate with the other trades on site and during their work spread more paint on the floor than on the walls.
After completion, they and the architect were asked three times to fix the insufficiently done work. Each time without success.
A key event was when our tiler left the construction site one evening after 7 pm and naturally locked the construction site door because the entrance area had just been newly tiled.
The painters were still on site after that. Because the construction site door was locked, they simply broke it open, walked over the freshly laid tiles and made another attempt to fix their insufficiently done work.
The next morning the tiler called and informed us, and the police were notified to record the damage.
Again, the architect tried to calm things down... the work was not that bad and still acceptable, and breaking open the construction site door was common practice on other construction sites.
We have now brought in a sworn expert who confirmed our suspicion. The work was performed poorly to unsatisfactorily. Estimated costs for corrections are around 6000 euros. In addition, he could not understand how the construction management allowed things to get this bad.
We have now handed the whole matter over to a lawyer.
My question:
To what extent can the construction management be held responsible, who was significantly involved in many problems?
Can deductions be made on the final invoice? And if so, would this hold up if he legally challenges it without prior warning?
 

HilfeHilfe

2017-11-17 09:36:13
  • #2
That is assessed by the lawyer / courts...

Do you have the written correspondence? If it is word of mouth

then....

Layperson's opinion
 

Jetset

2017-11-17 09:49:01
  • #3
Hello, the appointed RA is now only taking care of the painting company. We have not given the construction manager a written warning for fear that he would then not take care of it at all and that there would be even greater delays. But most of it can be proven through the email correspondence. And to my knowledge, a commissioned construction manager must keep a kind of construction site diary where surely a lot would become clear. Our mistake was that we relied too much on him and that we ourselves had too little knowledge of the subject...
 

HilfeHilfe

2017-11-17 12:36:39
  • #4
is also a bit too late, right? Construction is obviously finished, with defects, but finished
 

Jetset

2017-11-17 12:51:37
  • #5
No... we are inside... but it is far from finished. Electrical, painting, drywall, and window work are not yet completed and no final invoice has been received.
 

Knallkörper

2017-11-17 16:52:58
  • #6
Evicted without inspection? Serious mistake.
 

Similar topics
01.04.2020Construction Manager Area Neukirchen-Vluyn (Duisburg/Kleve/Wesel)10
13.11.2013Do you absolutely need an architect?10
21.08.2014Construction costs when building with architects. What does your experience say?18
19.12.2014Finding architects - but how?26
27.05.2015Does an external chimney have to go down to the basement?12
09.12.2016Planning/Floor plan single-family house (approx. 140 sqm, basement, ground floor, attic)30
12.10.2017Cost of enclosed space. First draft discussed with architects27
17.10.2017Construction costs for a single-family house 190m² + basement including a granny flat28
27.10.2017Construction description by architects: Who has experience?13
13.11.2017Construction scheduling - Who has to create it? General contractor, site manager?11
12.01.2018Building height of 8.5 m with basement and 2 full floors31
14.03.2018Slight slope, building with a basement or a floor slab?16
07.02.2018Architect's suggestions disappointing - What next?32
14.03.2019City villa with approx. 200 sqm - without basement. Please provide feedback50
26.01.2019Semi-detached house on a hillside with a basement, looking for a floor plan.17
11.02.2019Floor plan of a single-family house on a hillside with a basement19
01.08.2019Building with architects - experiences, tips?31
11.07.2019Possibility of preliminary questions to architects23
02.12.2019Single-family house (2 floors + residential basement + developed attic) approximately 200 sqm - changes162
27.06.2020Level the basement or the plot?43

Oben