motorradsilke
2022-08-17 16:11:26
- #1
No, mostly not. Plaster + screed leave some space. Door only at the very end and it is slightly reworked.
In my case it was an exception because there was a misunderstanding with the contractor. Normally they would also be in before the interior and exterior plaster.
That's how I know it too. And the electrician clearly said that he does not lay any cables before the house is lockable. Not only with us, but always. And cables always come before plaster.