Costs numbering property developer/self-purchase/goods/assembly - ok?

  • Erstellt am 2016-08-12 21:21:58

EA-Tec

2016-10-04 09:14:38
  • #1
Even though the last post was already a few weeks ago, I would still like to briefly comment on the price difference.

For us, it is about a main bathroom as well as a guest bathroom in a new build apartment. The standard is a joke, and the surcharges for our desired products from the new build plumber are outrageous... he wants EUR 17,000 (the installation etc. is, mind you, already included in the purchase price of the apartment - the higher effort for the larger washbasin, for example, will not cost thousands of euros), another plumber does the same for EUR 12,000, including installation. If I buy the items (even the accessories etc.) myself, I end up at EUR 9,000... for EUR 3,000 I can find enough craftsmen to install a few bathroom furniture pieces for me.

And now I ask myself
a) EUR 5,000 surcharge at the plumber commissioned by the project company... for what?
b) what do I have in case of warranty? Will the plumber take the blame? Hardly! I claim that in case of emergency, the nasty finger-pointing will start!

If I commission the new build plumber, I could blame everything on the project company if something goes wrong... however, they will blame the plumber, and he will blame material weakness or something else.

So why not buy everything myself and commission someone? After all, we are talking about at least EUR 5,000 savings!

I will give the plumber commissioned by the project company a chance and politely but firmly tell him that he should please reconsider his offer... if that doesn’t work either, it’s out for me - but that certainly won’t bother him, as the project company is currently building a total of 160 apartments in the district, and he has been commissioned for the installation everywhere.
 

HilfeHilfe

2016-10-04 09:21:56
  • #2
You must always keep in mind that with 160 apartments you have zero negotiating power... Whether you feel more comfortable with an external plumber in the next 5 years is a decision you have to make.
 

EA-Tec

2016-10-04 09:25:39
  • #3
We already know which bathroom furniture we want - whether the project plumber installs it or a plumber commissioned by us makes no difference. The desired products should be installed and commissioned, and ideally I won’t have anything to do with the plumber for years.
 

EA-Tec

2016-10-05 22:27:24
  • #4
Spoke with the paramedic yesterday - "I don't make any money on it and only add 30% because of the warranty"...

Much respect... "only 30%"... my definition of "not making any money" differs quite significantly from that of the [Sanitär-Betrieb].
 

Similar topics
11.06.2013Radiator in the new building?13
22.11.2013Costs of inheritance, demolition, new construction15
06.02.2017Insulate new construction 36.5 aerated concrete?60
16.05.2014What makes a new building expensive?20
15.06.2015New construction: Plaster the concrete ceiling on the ground floor18
18.01.2015New construction Kfw70 underfloor heating and tiles11
08.01.2015How is the amount of the land charge determined in the case of a new construction?14
31.12.2015Preparing electrical work for a smart home new construction17
07.01.2016Are cold corners in new buildings still contemporary?13
18.08.2016New construction with sand-lime brick + ETICS - Criticism?!32
04.01.2017Plaster walls in new construction or use fleece?16
30.09.2018BAFA funding for air-water heat pumps in new construction - how does it work?30
30.11.2017Gas and electricity consumption in new construction16
12.01.2018Possible thermal bridges in house wall corners in new construction10
03.01.2018Demolition and rebuilding or renovation? Which house?13
11.12.2019New double garage / workshop13
08.04.2020Wall tile in the bathroom cracked after 8 months, new construction12
23.07.2020New construction extremely noise-prone or sensitive to sound26
31.03.2021Repair thermal bridge new construction13
20.09.2024New construction - Costs of plumbing & heating experiences?15

Oben