Hello Kati,
as far as I know, the headquarters and also the facility center are in Nordhorn.
Seen from the Rhineland .... approximately Hamburg
However, I also have to state here that there are still some unclear points in the construction and service description. For example, earthworks are included but not the removal of materials, etc.
That is normal because the providers do not yet know anything about your property, the soil conditions, etc. – how should they then calculate the removal reliably?
Since our plot is already quite expensive, the offers are at the limit of what is feasible. Therefore, I need to know quite exactly what else would come at us.
Look, I give this list to every interested party during the first consultation. On the one hand, because I know that some "competitors" sugarcoat these figures and on the other hand – even if I might not win them as a customer – so that they do not fail with their financing, at least in this point.
Additional construction costs that should be considered in every house construction/financing calculation:
1. Plot
- 3.5% real estate transfer tax – varies by municipality
- possibly brokerage fees, approx. 3.5% of the plot price – varies by municipality
- approx. 1.5% notary fees, calculated from the plot price, 3 x entry in the land register (1. reservation of conveyance, 2. transfer of ownership,
3. entry of the mortgage)
2. Financing
- possibly advisory/closing costs for financing, approx. 1.5% of the entire loan amount
- approx. 0.25% commitment interest, based on the loan amount
3. Construction preparation
- approx. €2,800 - €3,200 surveying services (qualified site plans / height survey /
staking out / building survey)
- provision of connections for construction water / construction power, approx. €6.00 - €8.00 rent for standpipe/day,
approx. €300.00 rent for construction power meter and its consumption costs
- fees (for house number, drainage permit, building permit), approx. €1,000.00 –
€1,500.00, varies by municipality
- builder's liability insurance approx. €80 - €150.00/year, depending on the insurance company
3. Earthworks
- removal of excess soil (normal soil conditions) for cellar, approx. €1,500.00
- internal development (wastewater/rainwater pipes), approx. €2,500 – depending on pipe route
- inspection shafts, soakaway or infiltration shaft, approx. €1,900.00 - €2,200.00
4. House connection costs
- electricity/gas/water/telecom, connection to the sewer, approx. €8,000.00 - €8,500.00 – varies by municipality
5. Fees
- acceptance of the drainage line, approx. €150.00 – varies by municipality
- chimney sweep (acceptance of chimney / gas system - note fee charged twice),
approx. €200.00 – varies by municipality
- cadastral office (transfer of surveyor's data into the property map), approx. €150.00 – varies by municipality
6. House
- painting/wallpapering & floor coverings, textured wallpaper and tiles done as own work
approx. €4,000.00 - €5,000.00
7. Outdoor facilities
- outdoor facilities (pavings), own work approx. €2,000.00
- terrace (earthworks, slabs), own work approx. €2,000.00
Total approx. €30,000 - €35,000