Anniiii
2025-02-09 08:17:53
- #1
Reminding or issuing a reminder initiates a legal process that must be usable in court if you need to sue.
It won't be that simple: if there is no default clause (50€ per day or so) with some small print, then you shouldn't expect anything.
Provision interest is out of the question anyway. There's nothing for that because financing is your personal matter. The smart builder includes provision interest in their calculation of additional construction costs.
And my personal opinion: don't terminate too early. Parallel costs must be expected.
Our contract contains the following passage:
The contractor commits to completing the property ready for occupancy by 12/01/2024 and to full completion by 12/30/2024.
The start of construction is scheduled for xx.xx.xx.
The contractor shall only be responsible for a delay in occupancy completion if it is attributable to fault on their part.
The construction of the building project must be carried out according to the plans and the building description.
So that means we have no claim? For anything? At the time, we were pressured to sign the notary contract even though the floor plan and building description had of course not yet been adapted to us. After all, they said they are not a prefab house company, but that we could still adjust everything and make changes during construction. That is true regarding the equipment..
We now suspect a financing bottleneck due to another construction site, which is why there was no progress for weeks at times. Even after the demolition of the old building, nothing happened for months. And we have to pay for that now? Also, that we already had to take out a loan 10 months before the first partial invoice seems outrageous to me in retrospect. He had a financing confirmation after all...