I would get more detailed information on that. For us, it is the same as for you, meaning that the lines up to the property and the inspection shafts were already included in the property price.
However, the following still apply:
- €11,000 for electricity, water, district heating, and fiber optics to the [Stadtwerke]
- €5,000 for wastewater to the civil engineer for connection of the house with inspection shafts.
So a total of €16,000, which should not be forgotten...