Architect --> Agreements? What is that?

  • Erstellt am 2013-10-24 12:24:54

€uro

2013-10-25 10:23:35
  • #1
Certainly a decision that you will very likely not regret!!! However, it assumes that with the new concept, a sufficient basic investigation as well as system dimensioning is available! Then hardly anything should go wrong and you can expect reasonable consumption costs! Best regards
 

Bauexperte

2013-10-25 14:48:42
  • #2
Hello Yvonne,


If your statement is meant exclusively, you are wrong. Otherwise, a clear yes and no ;)

There used to be – nowadays less so because architects are wary of liability risk – both combinations. A contract for the architectural services according to HOAI and a separate contract for the new building itself; the architect acted as planner and construction manager in one person. Not infrequently, both were combined in a single contract for work and the architect was considered a classic general contractor.


Only if there is a single contract with the architect for all necessary planning stages. Then the architect prepares the tenders and the principal/client decides based on sampling and price.


That or nepotism – one of these two is highly likely to be true.


You don’t change a thing there …


Only if and as contractually agreed.

Rhenish greetings
 

ypg

2013-10-25 20:23:58
  • #3
Look, learned something new about [Architektenleistungen] again :)
Thanks!
 

dessin

2013-10-27 19:32:25
  • #4


This certainly does not correspond to the usual procedure of an architect.......
If still possible and if the construction is not too far advanced, I would try to change.
It would make sense to hire an interior architect or an architect with experience in interior finishing.
In which federal state is the construction site located? Best regards
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18

Oben