R.Hotzenplotz
2017-10-17 22:09:11
- #1
Hello,
we have a contract offer from the general contractor (GU) for our house construction and have also consulted a construction advisor. Some things that are still "open" after a conversation with the GU are the following, and I would be interested in practical experiences / assessments on the following points from other users.
1) The construction advisor was of the opinion that I should have a penalty clause included in the contract. The GU says that this is not common for private projects; the Construction Code law protects me anyway in terms of damages should the construction time be exceeded. Nothing regarding damages needs to be included in the contract because the Construction Code automatically applies.
2) The construction advisor also criticized that the contract does not mention a completion guarantee in the amount of 5%. The GU again refers to the Construction Code and says that inclusion in the contract is therefore not necessary.
In this context, there was also a small disagreement regarding the actually fair payment plan. The construction advisor said the last installment payment after acceptance & defect rectification should rather be 3.5% instead of 2% as stated. The GU says that since we still have the completion guarantee, which we only release when all defects are corrected, we effectively already have a 7% retention with the standard regulation. He does not want to agree to 3.5%. I am particularly curious how this is assessed.
3) The contract includes construction supervision as quality assurance. We actually wanted to remove this because we are commissioning our own expert anyway. But this is not possible. Is it common that this cannot be removed? I understand the GU’s position that especially because people sometimes have their own expert, they need this so that our expert does not drive the site manager crazy. But on the other hand, I have to pay for it. The 4-phase supervision is included in the house price at about €4,000. Alternatively, I was suggested that we can jointly agree on an expert, e.g. from DEKRA. My expert cannot do it because he belongs to the Association of Private Homeowners.
4) The construction advisor recommends including parts of the earthworks under the GU contract because he sees warranty interface issues here. Specifically, he says the soil report requires gravel to be backfilled beneath the dimpled membranes. This should definitely be commissioned through the GU. The GU on the other hand says he has deliberately excluded the earthworks because these can be very variably expensive and he cannot include them in the GU contract without high risk surcharges – so the entire earthworks topic will be tendered.
5) Otherwise, the construction advisor said he has often (with other providers) experienced that additional costs for height adjustments were charged afterwards. He mentioned €8,000. Therefore, one must be careful to include the date of the last height adjustment in the contract. The GU could not make any sense of this. Has anyone ever encountered something like this?
It should be enough to refer to the building application in the contract, shouldn’t it? All heights are included there.
All in all, the feedback from our construction advisor was that we have a pretty fair contract in front of us. He has already had tougher cases.
we have a contract offer from the general contractor (GU) for our house construction and have also consulted a construction advisor. Some things that are still "open" after a conversation with the GU are the following, and I would be interested in practical experiences / assessments on the following points from other users.
1) The construction advisor was of the opinion that I should have a penalty clause included in the contract. The GU says that this is not common for private projects; the Construction Code law protects me anyway in terms of damages should the construction time be exceeded. Nothing regarding damages needs to be included in the contract because the Construction Code automatically applies.
2) The construction advisor also criticized that the contract does not mention a completion guarantee in the amount of 5%. The GU again refers to the Construction Code and says that inclusion in the contract is therefore not necessary.
In this context, there was also a small disagreement regarding the actually fair payment plan. The construction advisor said the last installment payment after acceptance & defect rectification should rather be 3.5% instead of 2% as stated. The GU says that since we still have the completion guarantee, which we only release when all defects are corrected, we effectively already have a 7% retention with the standard regulation. He does not want to agree to 3.5%. I am particularly curious how this is assessed.
3) The contract includes construction supervision as quality assurance. We actually wanted to remove this because we are commissioning our own expert anyway. But this is not possible. Is it common that this cannot be removed? I understand the GU’s position that especially because people sometimes have their own expert, they need this so that our expert does not drive the site manager crazy. But on the other hand, I have to pay for it. The 4-phase supervision is included in the house price at about €4,000. Alternatively, I was suggested that we can jointly agree on an expert, e.g. from DEKRA. My expert cannot do it because he belongs to the Association of Private Homeowners.
4) The construction advisor recommends including parts of the earthworks under the GU contract because he sees warranty interface issues here. Specifically, he says the soil report requires gravel to be backfilled beneath the dimpled membranes. This should definitely be commissioned through the GU. The GU on the other hand says he has deliberately excluded the earthworks because these can be very variably expensive and he cannot include them in the GU contract without high risk surcharges – so the entire earthworks topic will be tendered.
5) Otherwise, the construction advisor said he has often (with other providers) experienced that additional costs for height adjustments were charged afterwards. He mentioned €8,000. Therefore, one must be careful to include the date of the last height adjustment in the contract. The GU could not make any sense of this. Has anyone ever encountered something like this?
It should be enough to refer to the building application in the contract, shouldn’t it? All heights are included there.
All in all, the feedback from our construction advisor was that we have a pretty fair contract in front of us. He has already had tougher cases.