Hope dies last.
I received a call from Telekom yesterday, builder hotline. The young man told me during the conversation, sincerely, that our project had progressed quite quickly and I should consider myself lucky. There is the company SAG in our area, which manages our project in the background.
Today, it was finally time:
The mentioned company was standing in the yard, completely baffled. Reason: Telekom’s order to measure our connection.
APL was installed by SAG last week along with the laying of the power cable, wisely anticipated.
Only the connection to the main cable was missing. Where there is nothing, you cannot measure anything. The entire Telekom laying plan was, to crown it all, also wrong.
Hopefully the ordeal will end on Monday.
I’ll spare you the craftsmen’s curses. They were not mild.