Trouble with architect's bill for planned construction project

  • Erstellt am 2021-12-12 17:55:40

Araknis

2021-12-14 12:48:32
  • #1
I am so glad that our architect clearly stated before the first meeting that he only provides useful information for money and then more than fulfilled that. I like transparency. Especially in this sector, where in 99% of cases you are dealing with beginners on the client side. I find it fair, but handling it differently is also absolutely legitimate. Just go to the notary and ask him "just quickly" something :)
 

11ant

2021-12-14 13:46:33
  • #2

If you still haven’t understood the concession, then my explanations must rather have been "not long enough" :-( :

You can’t really "agree" with me on that, because I did not draw this conclusion (to give in as a perceived martyr). The architect does not demand the "maximum" (and certainly not "what she hopes to get"), but symbolically the remuneration of (in reality certainly more than just these) five working hours in the termination of a contract for work and services, in the fulfillment of which until the end she would have been paid much more royally than by the hour. In court (given the amount in dispute, the first instance here would be a regional court = with mandatory legal representation) this would have become a long story, but I will not let myself be reproached again for the "excessive length" for a more detailed explanation, so you will have to figure that out yourself. I had already hinted at the "constructive problem" of this legal question, so you basically just have to look back.

An oral contract was made here, and even if the OP did not specify exactly to what extent the activity was agreed upon – I am at least pleased that you correctly recognized that this extent must have at least been service phase 1. That this was not yet completed is inherent in the nature of the termination or premature cancellation – thus she omitted the completion of service phase 1 not maliciously, but at the client’s request. Therefore, her work up to the termination of service phase 1 is to be remunerated, and the alternative billing of the effort by working hours is perfectly appropriate and in doubt, in my opinion, clearly unfavorable to her in a fair middle ground settlement – the latter is part of what I mean by "generous"; furthermore, by waiving a contentious dispute, she saves the OP fees which would be multiple times her claim in each of the two parts (the OP’s lawyer and court as well as the opposing lawyer).
 

Similar topics
04.07.2015House contract with financing condition, lawyer wanted10
21.07.2020Lawyer wanted to sue the construction company52
11.04.2020Construction law - hire a lawyer or not yet16
26.04.2020Are phases 1-4 sufficient? Or additionally 5?11
22.05.2022Are performance phases 1-3 with the architect and lump sum offer somehow disadvantageous?19
18.01.2023Architect performance phase 1-4 - Which documents are required?33
28.06.2024Building permit - is a lawyer useful?12
28.09.2024Architect commissions surveyor without the homeowner's consent.45

Oben