f-pNo
2014-04-04 15:26:36
- #1
Hello everyone,
thank you very much for your support and your explanations.
Regarding my question about shrinkage cracks, the site manager explained to me that they exactly use this method with the keyhole cuts. If this is an established and proven method and is acceptable so far, I will leave it at that.
That is actually how I feel. The company has also addressed certain points and revised their construction performance description once again. In addition, the supplementary agreements were revised as well, so unresolved points were fixed. Thus, the work of the Bauherren-Schutzbund has already helped me. However, there are three points in the contract in particular on which the Bauherren-Schutzbund insists and where the company believes (probably after consulting a construction law attorney) that they will not be changed. Besides the above-mentioned point, it concerns the payment plan. After the shell construction phase (including roofing and partially plumbing work), the company calculates about 60% of the costs. The construction performance description states that it should be a maximum of 50%. However, the company explained to me that this 60% also covers the costs for the earthworks (about 24,000 euros). From my point of view, the 60% is justified—thus acceptable to me. The Bauherren-Schutzbund would still have liked to enforce the 50%.
For the third point, I will open a separate topic because it would go beyond the scope here.
Many thanks for the information and the support,
thank you very much for your support and your explanations.
Regarding my question about shrinkage cracks, the site manager explained to me that they exactly use this method with the keyhole cuts. If this is an established and proven method and is acceptable so far, I will leave it at that.
You can tell from your question that you talk too much with the person from the Bauherren-Schutzbund. As a result, exactly what I don’t appreciate about their offers happens. You as the client are more unsettled than enlightened, and you are still paying for it.
That is actually how I feel. The company has also addressed certain points and revised their construction performance description once again. In addition, the supplementary agreements were revised as well, so unresolved points were fixed. Thus, the work of the Bauherren-Schutzbund has already helped me. However, there are three points in the contract in particular on which the Bauherren-Schutzbund insists and where the company believes (probably after consulting a construction law attorney) that they will not be changed. Besides the above-mentioned point, it concerns the payment plan. After the shell construction phase (including roofing and partially plumbing work), the company calculates about 60% of the costs. The construction performance description states that it should be a maximum of 50%. However, the company explained to me that this 60% also covers the costs for the earthworks (about 24,000 euros). From my point of view, the 60% is justified—thus acceptable to me. The Bauherren-Schutzbund would still have liked to enforce the 50%.
For the third point, I will open a separate topic because it would go beyond the scope here.
Many thanks for the information and the support,