Refusal of building acceptance due to outstanding work?

  • Erstellt am 2019-11-06 16:17:41

chrisw81

2019-11-07 09:25:06
  • #1

I’m afraid that too, that I will be chasing after some workers forever.
I want to move in within 3 weeks and not live with this situation in the living room forever.
Painters still have to come again, etc., you can see the touch-up paint, and so on.
 

Climbee

2019-11-07 10:21:06
  • #2
So what I still haven't quite understood: were the windows moved because it was a (subsequent) wish of yours or because they were not installed according to plan and you then insisted on having them moved (according to plan).

In the first case, I can understand the general contractor not wanting a delay - however, I would then not understand why this has so far been at no additional cost to you.
In the second case, I would - quite clearly - stay firm and not accept it.
 

chrisw81

2019-11-07 11:16:30
  • #3
There was no "plan" for the windows and it was more of an aesthetic defect (the inner window surface was much too deep, resulting in hardly any windowsill being present, the reason was the very deep roller shutter housing of the Raffstore). After a threat with a lawyer, everything then went very quickly and everything was moved without cost. Whether they moved it out of kindness or for other reasons, I don’t know. At least I was never told that I had to pay for it.

So it’s rather a mixture of both cases you described... Of course, I would first try to remain stubborn until they can legally/contractually object to me.
 

Matthew03

2019-11-07 11:24:52
  • #4
with lawyer

...Oh, with this kind of interaction, one should know the background(s)...
 

fragg

2019-11-07 11:33:02
  • #5
because you are only allowed to move in once the house is reported as completed to the building authority, and you can only do that once it has been accepted. and because depending on the situation, you may not be allowed to move in because you might not have the right of habitation. moreover, moving in is practically equivalent to an (defect-free) acceptance. if you build according to VOB, the subsequent trade must report defects. if the subsequent trade simply starts work, the preceding trade is considered accepted as defect-free. are you already painting? possibly the plastering work is already tacitly accepted as defect-free.
 

chrisw81

2019-11-07 11:40:46
  • #6

Well, I said that I would involve a lawyer if they did nothing. Whether I really would have done it, I don't know. But the threat worked. I believe nothing works without such threats otherwise...
 

Similar topics
27.02.2015Burglary-proof windows?33
03.06.2014Interior design - windows14
16.01.2018Is an extra charge for colored windows realistic?19
18.06.2014Inspector defect identification, determination of window installation10
18.05.2016Help needed with window arrangement!32
27.05.2015Huge problem with condensation on the window34
04.07.2015House contract with financing condition, lawyer wanted10
10.05.2015Screed uneven - defect removal refused52
03.06.2016Built-in windows do not match the window plan. Objection?16
22.05.2017Almost every window has scratches - what is considered normal?22
28.11.2017Every word penetrates through the windows. Is it the same with you?21
13.07.2018Corners of the new windows are very dirty or scratched46
21.06.2019Window - Incorrect advice, wrong window product installed44
21.07.2020Lawyer wanted to sue the construction company52
24.12.2019Height of the fence to the neighbor and windows in the boundary construction59
24.12.2019Windows are smaller than in the building application/work plan.40
11.04.2020Construction law - hire a lawyer or not yet16
16.05.2021Handle position on the window not centered - defect?51
02.11.2021Bathtub in front of window, railing too low, contractor is obstructing48
28.06.2024Building permit - is a lawyer useful?12

Oben