Built-in windows do not match the window plan. Objection?

  • Erstellt am 2016-06-01 00:17:28

Bieber0815

2016-06-01 20:48:12
  • #1
I would have thought so too, but: Besides, one would have noticed it before installing the windows (because you do measure afterwards ). So: Are you sure the shell construction is correct?
 

Bauexperte

2016-06-01 22:03:19
  • #2

I do not doubt that the shell construction measurements are correct. If that were the case, the OP would surely have mentioned something about it.

I assume that the window opening was left out in the wrong place (measured -8 cm from side x).


Construction expert on the go
 

Bieber0815

2016-06-01 22:56:31
  • #3
That is a contradiction to me.
 

Otus11

2016-06-01 23:11:20
  • #4


1.
Botched construction remains botched construction – and thus a "defect". Before and after acceptance.

Acceptance is merely the point in time when the legal nature of a claim due to "defects" changes from the so-called obligation to perform into a warranty obligation.
In other words: With serious defects before acceptance, as a contractor I may not yet have "performed"; after acceptance, it is a warranty claim (for which the burden of proof reverses after acceptance).

2.
The first question here is whether extensive subsequent performance can also be demanded for (visual) defects – or whether that would be disproportionate:

§ 635 III Building Code
The contractor may refuse subsequent performance without prejudice to § 275 (2) and (3) if it is only possible with disproportionate costs.

Meaning:
If a contractor refuses to remedy the defect due to disproportionately high effort (§ 635 (3) Building Code), they are still liable to the client for damages because of the defect.
However, the client cannot then claim the costs of defect remediation as damages, but only the reduction in value of the construction. To avoid contradiction, case law holds that damages cannot be claimed in the amount of the defect remediation costs when those costs are disproportionately high (because they would also be disproportionately high!). Rather, in this case, the client can only calculate their damage based on the reduction in market value.

3.


If that is the case, then it is not a planning error but an execution error.
Then it is not just a visual defect, but actually affects the dimensions: One wall panel is 8 cm too long, the other side 8 cm too short. For example, do the 82 cm that are drawn as wall width in the corner in the first drawing on the upper floor correspond? Or was the lower window on the ground floor shifted to the right? There are no dimensions there.
Anyway, that is not how the OP created it; the drawings show congruent line alignments.
Is there a clause in the contract about the priority or binding nature of drawings?

4.
Central question therefore: Is subsequent performance disproportionate?
It depends....

If the overall weighing of interests shows that the appearance is of secondary importance and the defect does not lead to any functional impairment, the contractor can refuse subsequent performance more easily than if the client's interest is also directed at a visually flawless service. This would be the case, for example, with high-priced works or special mention in the contract. For example, in the purchase of a new car, a slight deviation in the shade of color was already considered a defect.
 

Bauexperte

2016-06-01 23:35:48
  • #5

The opening in the masonry for the window is correct; the element 2.26 x 2.135 m can be installed.

According to the manually created attachment, the green window reflects the planning, the red window the actual condition.



Construction expert on the go
 

kbt09

2016-06-02 05:56:04
  • #6
The casus knactus is surely that the wall openings were known and were probably made correctly


and



What was not known and was probably only determined by the window manufacturer or whoever ???? is the width of the corner support. In the remaining ground floor section, the window was then split again. However, the center point of the two doors shifted further to the right according to the plan (downwards to the left in the view), due to the widening of the corner support, resulting in this outcome.


So in my opinion, what was missing was the correct calculation of the corner support and THEN the exact planning of the window opening positions.

The question here would be who could have calculated the corner support when and whose responsibility it would have been. Based on the drawings, I would say that something additional would have had to be agreed upon, because the drawing explicitly states that the corner support is to be calculated according to the structural analysis. So it could be wider or narrower than drawn.
 

Similar topics
13.09.2012Feeling pressured into a contract, is that normal?17
27.02.2015Burglary-proof windows?33
03.06.2014Interior design - windows14
16.01.2018Is an extra charge for colored windows realistic?19
18.06.2014Inspector defect identification, determination of window installation10
01.07.2015Builders' legal protection insurance35
07.04.2016Defect?? Glued engineered parquet doesn’t stick everywhere?!11
04.07.2016Building without a contract - Concerns?39
22.05.2017Almost every window has scratches - what is considered normal?22
28.11.2017Every word penetrates through the windows. Is it the same with you?21
13.07.2018Corners of the new windows are very dirty or scratched46
14.04.2020Security deposit according to §650 of the Building Code20
13.07.2020Developer does not want to offset lump-sum damages with installments19
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
10.04.2021Delays with the general contractor, no deadline set according to § 650 Building Code65
16.05.2021Handle position on the window not centered - defect?51
02.11.2021Bathtub in front of window, railing too low, contractor is obstructing48
19.03.2023Consumer construction contract, construction contract not executed - compensation for damages?44
06.09.2024Contractual penalty in the Building Code contract - new construction20

Oben