Malli
2016-02-02 22:38:54
- #1
The screed was laid on 22nd/23rd January with an additive, and the tilers started on 28th January. They worked hard, as they were only allowed to ventilate very carefully, and the heat pump's heating program was switched on on 26th January. A very ambitious schedule, but the developer is liable for every tile that cracks, since they are also their tilers. Next weekend, our 10-day time window for painting work begins - with painter’s fleece on the ceilings to come back to the original thread [Malervlies]. On the walls, the Erfurt Flaxx 100 non-woven wallpaper will be applied. I am curious whether there will be enough time for some filling, sanding, priming, wallpapering... We will probably only manage to paint later. Moving date is 15th March.