Is the schedule for construction in winter realistic?

  • Erstellt am 2016-11-14 15:35:56

Svetta16

2016-11-14 15:35:56
  • #1
Hello :)

we are now right in the middle of the construction process, the ground slab was poured a week ago. The plan is for a solid bungalow with wood cladding. Our original plan foresaw completion by the end of April. This was planned with a lot of buffer time back then. However, we have used up this buffer due to various delays in the building permit.

Our architect (who is also the construction company) says that the weather only plays a minor role. The earthworks are done and now it is important to finish the shell soon so that the weather no longer has such a strong influence, but the rest will be handled with dryers and the like. A friend who also works in construction was very confused, however, that the shell and so on are actually supposed to be done in these weeks, because it "will never be dry."

From my previous experience, most construction activities used to be paused in winter. Are the new materials really better suited, should we prepare for a delay, or is there even a risk that there will be consequential damages later because construction took place during frost or cold?
 

Musketier

2016-11-14 15:46:14
  • #2
Depending on the weather, a house without a basement can certainly be completed within that time if the shell can still be erected and the roof is on. Inside, if necessary, construction heaters can be used to achieve the required temperatures, for example for the electrical work. However, I would not rely on the deadline at the end of April and terminate the apartment lease already. You yourself have noticed how quickly the buffer disappears and the construction work hasn’t even started yet. There was just a post in the forum where someone moved into the house without heating. This counts as acceptance and should be strictly avoided.
 

ypg

2016-11-14 16:30:35
  • #3
It is possible, not unlikely either.

Nevertheless: I wouldn't rely on this date at all, it is also quite likely that the house will only be finished at the end of June. The completion of a house depends on many factors, mostly on many companies that have to work hand in hand independently. Then there is the drying time factor, which can hold surprises... Our bricklayer still said in July that we _could_ move in at the end of September. Could! The handover was at the end of January.

Regards
 

Bieber0815

2016-11-14 16:40:09
  • #4
That’s fine as it is. Now it depends on the actual temperature and weather conditions. For all building materials (mortar, adhesive, foam, etc.) there are processing guidelines that specify the permissible (and possibly also recommended) limits. In case of doubt, you have to get corresponding evidence. You can also work with additives (concrete processing ...). If now severe, persistent frost comes, it looks tight, but a late autumn as usual in recent years should not greatly slow down the construction project. And once the roof is on and the windows are in, then everything is possible anyway. (A bungalow shell construction only takes a few days if necessary; assumption: wooden beam ceiling.) The completion date can be met but does not have to be. I dare to assert that weather has the least influence on it ;-). At least that seems to be the rule in most construction projects.
 

Bauexperte

2016-11-14 16:48:02
  • #5
Hello,


That is not correct. The weather only plays a minor role as long as the temperatures are above 5°C; below that it is critical. For example, if masonry work is carried out at too low temperatures, mortar and adhesives do not hold, and the risk of later cracking increases. Reinforcing steel must be warmed above 5°C.


That is correct as far as the weather allows the complete finishing of the closed shell!


It is less about improved products than about the client's desire to move in as soon as possible after signing the contract.

Winter weather is a recurring annual issue; in recent years the construction industry has been favored. Whether this will be the case in 2016/2017 cannot be answered reliably by anyone; if it goes wrong, it will be cold until Easter. So in your place, I would not terminate your apartment yet.

Best regards from the Rhineland
 

Svetta16

2016-11-15 10:24:34
  • #6
ok, that should explain why the work is currently paused. The last few days we've had quite low temperatures here. But it’s supposed to get warmer again now. So I’ll keep my fingers crossed myself that this warm phase lasts a bit and is enough to build our walls ;)

And yes, it will be a wooden beam ceiling, so that seems like it might actually fit after all.

Apartments will be given notice no earlier than 3 months in advance, so in January, and then it should be somewhat clearer what the status is or rather the overall weather situation won’t be as decisive anymore but rather the trades ;) .

Move-in definitely only when everything is finished, we agree on that. Then if necessary better to store things and crash at the parents for a few more weeks, but we’re not moving into a construction site ...

Thanks for your input!
 

Similar topics
14.11.2011Shell construction still this year15
27.02.2015Purchase shell construction and complete it including financing15
11.02.2016Cost per cubic meter of built-up shell space14
16.02.2016Question about contractual completion14
03.09.2016Buy the kitchen more than a year before completion?54
07.05.2016Buying a shell construction - Experiences21
28.02.2017Are securities customary for completion and warranty?24
20.04.2017Payment plan with 35% after the shell construction, okay?10
06.09.2017Add a wind catch later to the shell construction17
07.10.2017From when must the shell construction be dry or sealed?16
16.11.2017Apartment renovated - unpleasant smell?!12
14.07.2019Costs for the shell construction of an office building16
28.10.2019Received an offer for my shell construction18
27.10.2019Water in the inner frame: Shoddy construction? (Shell construction)15
21.10.2019Construction start still this year (November)?14
28.05.2020Buy a 25-year-old shell structure42
15.05.2021How to calculate the quantity of materials for mortar and Ytong stones?12
12.11.2021Purchase of an old apartment, renovation costs21
14.05.2022Old building apartment with gas boiler - underfloor heating now, heat pump later14
28.03.2024Offer for shell construction of a single-family house 170 sqm - Is the price market-appropriate?57

Oben