Vicky Pedia
2020-01-05 19:03:48
- #1
What damage are we talking about here? The client ordered a functioning work that was to be constructed according to recognized rules of construction engineering. The fact that the structural contractor sees it that way as well is shown by the fact that they made corrections, just not professionally. The argument that they don’t earn anything from it also does not apply, since the structural contractor prepared the calculation themselves. You should request the structural contractor to properly construct the ceiling (4 weeks deadline). A retention in the amount of double the removal costs is possible. Just withhold 2,500. The structural contractor must prove to you that their solution was professional and desired. If they still have money outstanding, they will do something.