Tolentino
2020-09-17 11:50:06
- #1
So, I have to ask something here again. I have now ordered a HA column and already got the appointment. Does anyone know if I can now order house power instead of construction power? Of course, a distributor and meter have to be added, is it allowed to use a construction power box with meter space for that? Or do I still have to order a construction power connection despite the outdoor column. I'm asking here because the responsible contact person at Stromnetz Berlin is unfortunately on vacation. Maybe someone here knows. Thanks and regards Tolentino