danixf
2020-07-08 20:23:31
- #1
First of all, you are listing the net prices here. Gross it is €600. The difference here is also the earthworks. 3m from the property boundary. The other is 15m.Here I see it as the pillar costing €1070 and the box €1570, meaning only a difference of €500. That would already be great. Am I seeing this correctly? Or do I need both the pillar and the box if I want the connection laid into the house?
Depending on network coverage, you could be rejected for 50m. But since it's Berlin, it should work out.Also interesting is the point at the very bottom, especially for us, since 50m have to be laid to the back:
€15.19 per meter including VAT. 3m are included. So you have to pay for about 47m. Plus your private cable.Additional payment per meter of extra length: €63.70 Price reduction per meter of own work on private property**: €50.60 We would provide the trench and empty conduits as "own work". Does the meter then cost us €50.60 or €13.10? ,