First move in - then plaster, paint, and install flooring

  • Erstellt am 2019-06-19 14:52:15

bazinga

2020-05-18 11:11:10
  • #1
I am addressing the question again here and would like your tips regarding the order of procedures.

We are getting a floating screed throughout the entire house (basement, ground floor, upper floor, and attic). The walls will be finished to Q2 standard. After handover from the developer, the DIY work begins:

    [*]Floor work
    [*]Wallpapering
    [*]Painting

In which order should one ideally proceed? The bathrooms will be done by the developer. My current understanding is:

    [*]Fill and, if necessary, level/sand the floor. Due to dust production, this is our first priority.
    [*]Fill the walls and apply painter’s fleece.
    [*]Painting
    [*]Lay the floors.

Is this order roughly correct? We would do the painting and flooring ourselves, and assign the first two steps to the tradespeople. Priority-wise, the kitchen area needs to be finished first, followed by the rest of the ground floor as well as the basement (for storage, laundry room, etc.) and the upper floor (bedrooms). The attic can be finalized after moving in.
 

Similar topics
08.12.2015Construction costs for KFW70 house with basement turnkey15
26.10.2012External perimeter insulation floor slab, basement mold risk11
27.05.2013Cost estimation: prefabricated house, basement, carport, single garage10
01.07.2013Additional insulation in the Ytong basement (36 cm)14
19.03.2014Cost for a new single-family house, 2 full floors, without basement18
13.08.2014Water intrusion in basement due to storm - insurance?17
03.02.2017Single-family house 2 floors without basement - floor plan - costs - feasibility?24
05.08.2014First offer, 157m2 with basement, KFW 70, garage14
30.09.2014New construction planning - single-family house 160 sqm without basement - floor plan, costs, etc..29
31.12.2014Get training equipment in the basement (new building)?14
06.10.2015Correct formulation for a waterproof basement11
06.05.2016Single-family house floor plan with basement, version 223
10.09.2019Trouble with the property developer, don't know what to do anymore13
15.09.2019Developer refuses to hand over documents32
28.12.2020House purchase with cracks in the basement20
29.08.2023The construction company is building a basement smaller than in the factory plan51
12.01.2025Comprehension question: Gable roof - load-bearing walls - floor plan11
23.01.2025Current price estimate: Ready-to-move-in single-family house with basement in Baden-Württemberg12

Oben