Hello,
so we are now ready The wall is standing ...
I have to bring up the topic again. I fired up various calculators and the result was a requirement of approximately 8.5 tons (buffer already included).
The soil will be used to fill the area between the wall and the property (previously a slope) and to patch up the "bumps" in places. Basically to level the property.
What should I pay attention to when ordering the soil? Few stones is clear, but what else?
Are we getting any deliveries at the moment or is it better to wait a little longer to start these earthworks? Unfortunately, I would have to distribute it with 2 friends and wheelbarrows / shovels.
so we are now ready The wall is standing ...
I have to bring up the topic again. I fired up various calculators and the result was a requirement of approximately 8.5 tons (buffer already included).
The soil will be used to fill the area between the wall and the property (previously a slope) and to patch up the "bumps" in places. Basically to level the property.
What should I pay attention to when ordering the soil? Few stones is clear, but what else?
Are we getting any deliveries at the moment or is it better to wait a little longer to start these earthworks? Unfortunately, I would have to distribute it with 2 friends and wheelbarrows / shovels.