Assignment Declaration of Credit

  • Erstellt am 2013-11-26 16:17:46

Bauexperte

2016-06-19 23:31:23
  • #1
And what is your question?

Rhineland greetings
 

Landschafter1

2016-06-20 06:58:04
  • #2
Is the general contractor allowed to stop construction without notice? Especially if I use the documented defects from the Association of Private Builders as a reason for withholding payment and have offers/ cost estimates for the renovation.

Greetings from Hesse
 

ypg

2016-06-20 07:31:36
  • #3


I don’t understand: how can one criticize the floor slab if the screed is already on top?

Regarding your question: of course, the general contractor can initially stop the work. He even must... If something is complained about, in practice that must first be fixed before the work continues. This can then take a few days to weeks until the defect or error is corrected by the responsible trade.

However, the identified construction defects should be submitted in writing and the general contractor should be given time to fix them.

I wouldn’t speak of a construction defect during the construction phase anyway.

By the way, a construction stop is only ordered by an authority.
 

Landschafter1

2016-06-20 08:30:05
  • #4
Our foundation slab is a thermal foundation slab - where the surface should be ready for covering, achieved by smoothing with the machine.

The general contractor was given a deadline by us to eliminate the defects by April 28 ... plus an extension, as he could not obtain parts for the distributor of the underfloor heating on the ground floor.

Unfortunately, to date he has not corrected a single "defect" to the satisfaction of my construction supervisor. And he was last seen on the construction site by subcontractors on May 18. They have now informed me that they cannot continue working due to missing preliminary work by the general contractor. I called him about this and he then said or sent me in writing (June 10) that he is carrying out the work stoppage (since May 18) due to the withholding.

Shouldn't he have notified me of this beforehand so that I could react accordingly?
 

Bauexperte

2016-06-20 13:54:48
  • #5
Hello,

I am not allowed to provide legal advice here, as this is exclusively the domain of consulting professions. Therefore, please understand my answer as a "personal opinion."


Yes, you have breached the contract unilaterally by not transferring the due payment for services rendered.


Offers for renovation do not interest anyone at first, because your contractual partner has the right to remedy defects. Only when a reasonable deadline passes without result may you commission a third party!

Unfortunately, you have an unfortunate combination of circumstances: on the one hand, a lawyer you engaged and a Verband Privater Bauherren advisor, and on the other hand, a general contractor who presumably made mistakes. In such situations, it is not uncommon that the problem is recognized but the willingness to develop solutions is neither visible nor present; all the more so if the owed payment for services is withheld. It is necessary for the parties to sit down at a table and talk... talk factually... talk problem-oriented... without mutual accusations; the goal is not to search for problems but to solve them.

From my point of view, your Verband Privater Bauherren advisor bears a special responsibility; I hope he can hold back? In my opinion, he _must_ act as a mediator, not construct threats with a wagging finger. He should take the pressure out of the situation, find a common _language base_ with your general contractor, and equally, you need to hold back. Because –

a) missing functional potential equalization/foundation earth electrode
is bad, no question, but not unsolvable

Everything else reads more like a slogan, in the typical vocabulary – if you have not formulated it yourself – of an association expert. Not exactly motivating for discussions, but by no means unsolvable.

Conclusion: the better educated, professionally and life-experienced the Verband Privater Bauherren advisor is – the higher the chance to complete the contract as owed and not have to settle opposing positions in lengthy court proceedings. Keep in mind – in house construction, parties always meet before the regional court… that takes time… costs a lot of money/nerves/time and usually ends in a settlement.

Best regards from the Rhineland
 

DG

2016-06-20 17:20:23
  • #6


Yes, but not an "assignment." The dilemma is that you don't need an FC and you don't get a bank guarantee, in other words: you cannot fulfill the contract. Which gives the general contractor the right to terminate the contract – but according to construction experts, this doesn’t bring him much besides trouble and losses.

Therefore, I would show the general contractor the savings book and hope for understanding. After all, it is not forbidden to have 100% equity capital.

Best regards
Dirk Grafe
 

Similar topics
29.09.2011Is construction pre-planning without signature / contract legally valid?12
31.05.2015Wastewater pipe concreted in the floor slab at the wrong location29
06.07.2015Experiences with building surveyors12
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
07.04.2016Defect?? Glued engineered parquet doesn’t stick everywhere?!11
04.07.2016Building without a contract - Concerns?39
09.07.2016Construction supervision in the Dortmund area: Association of Private Builders or SV11
18.08.2017First invoice for earthworks and base slab due25
23.05.2025Is membership in the Association of Private Builders worthwhile?36
10.08.2018Landscaping company - defects, high bill, no warranty?!13
17.08.2019Base plate - Reinforcement steel is sticking out12
21.01.2021Complaint - Rectifications for glass gallery railing26
17.04.2024The wall is not level on the base plate or protrudes by 2 cm26
17.10.2020The base plate was cast too large - it has now been shortened - is that okay?48
09.03.2021Withholding payment for defects in the shell construction74
03.09.2021Construction expert for the complete building or only final acceptance16
24.12.2021GU insolvency after acceptance - Open defects15
03.10.2022Building acceptance of new construction despite missing heat pump. Significant defects?50
19.04.2024Bank withdraws financing commitment due to defects20

Oben