HansDampf88
2022-02-17 12:05:50
- #1
Hello everyone,
our construction project will begin around mid-June with the earthworks. The building application and applications for house connections and construction power have been submitted, and the first trades (earthworks and masonry) have been fixed. The surveyor still needs to be commissioned for rough and fine staking. That is the current status. Construction toilet ([Kumpel baut nebenan]) is available.
Now, there is still some time until mid-June. We would like to use this time to already carry out precautions and preliminary work for the construction phase, which would otherwise cause additional effort and stress later on.
For example, I was thinking of getting offers for a kitchen made and selecting floors, tiles, and sanitary fittings, so that there is no longer a major coordination effort later on.
Does that make sense from your point of view, or is it a completely wrong approach?
What other preliminary work do you think could already be done now?
Best regards
our construction project will begin around mid-June with the earthworks. The building application and applications for house connections and construction power have been submitted, and the first trades (earthworks and masonry) have been fixed. The surveyor still needs to be commissioned for rough and fine staking. That is the current status. Construction toilet ([Kumpel baut nebenan]) is available.
Now, there is still some time until mid-June. We would like to use this time to already carry out precautions and preliminary work for the construction phase, which would otherwise cause additional effort and stress later on.
For example, I was thinking of getting offers for a kitchen made and selecting floors, tiles, and sanitary fittings, so that there is no longer a major coordination effort later on.
Does that make sense from your point of view, or is it a completely wrong approach?
What other preliminary work do you think could already be done now?
Best regards