Advance payment for the window installment

  • Erstellt am 2023-06-07 16:54:22

11ant

2023-06-12 14:57:44
  • #1
On the contrary: if the GC could be bypassed, his lawyer would tell him in case of a complaint that he could calmly declare himself not responsible. The electrical trade was either removed from the GC’s scope of services or would be deemed tacitly accepted at the moment you let your craftsman onto his work. Whether it is the same craftsman is irrelevant. What counts is whether he acts as an agent of the GC or as an independent contractor. For the electrician, this would mean that he would then provide warranty for ALL sockets directly to you; the keyword “upcoming trade” has been mentioned here several times—mostly in threads about self-procured washbasins. Legally, that’s not really different, although in this special case it is more clearly delineated. But even here, the roofer (or the GC regarding the roofing trade) could construct a tacit acceptance. Please do not lead possibly naive readers into such unfounded optimism. The GC only owes you his overall work to the extent that you have not reduced his scope of services. Conversely, you might also owe him the profit from trades that you awarded as upgrades with his tacit consent. Identity of persons of third parties, as said, does not fundamentally change that. How often do I have to say that the average private homeowner never operates on equal footing with the legal departments of the big names?
 

11ant

2023-06-12 15:10:45
  • #2

That would also be complete nonsense: a completion guarantee serves to secure the completion of the overall work by the GU; the GU is not responsible for Hermes guarantees regarding its subcontractors.

How far away from the windows are you currently: foundation earth electrode, ring beam, ... ?
 

Bayernbors

2023-06-12 15:23:12
  • #3


I have not applied for a completion bond. I understood this statement to mean that it is only possible to obtain a guarantee for this advance payment.



We are still in the demolition/earthworks phase. It will take several more months until the shell is finished and the windows are ordered.
 

Similar topics
10.02.2020Must the construction company itemize the costs per trade?13
22.04.2021Costs for the heating & sanitary trade86

Oben