Additional financing. Bank wants a breakdown of construction costs

  • Erstellt am 2022-08-02 10:25:16

Zinada1

2022-08-02 10:25:16
  • #1
Good day,

unfortunately, we need to refinance €30,000 for our construction project. Although we had planned a buffer when finalizing the financing, the costs for the earthworks have significantly exploded. Due to pile foundation, excavation, construction road, as well as the beam grid for the pile foundation + waterproof concrete slab, the costs amounted to nearly €100,000. We had planned €50,000 as a buffer, and we were able to save €20,000 in the last 8 months.

We have taken out 2 loans. 1. through an insurance company with a term of 36 years 2. €150,000 through the KFW.

Our bank advisor recommended that we arrange follow-up financing through the KFW. Now they want a cost breakdown from our developer including all additional costs. However, we assigned all the earthworks as own work, and our developer had nothing to do with it. The price of the house has not changed since the financing was finalized; only the earthworks caused additional costs.

How do I now correctly communicate this to the bank? Should I prepare a separate cost breakdown for the earthworks? Our developer does not want to sign for the own work.
 

ypg

2022-08-02 10:33:31
  • #2

That doesn't matter. Just list the additional earthworks and attach the invoices. Possibly also the transfer of the 20,000€ from your liquidity. That should be sufficient.

The bank naturally wants to know that they are not financing your new car or furniture, but that the additional money went into the house construction.
 

HilfeHilfe

2022-08-03 07:20:44
  • #3
Document the earthworks with a quote or the invoice. Should be sufficient
 

Grundaus

2022-08-03 08:42:40
  • #4
Did I understand correctly that the earthworks have become 100,000.-€ more expensive? If so, it is quite normal for the bank to become suspicious. Even a first-semester architecture student cannot make such a miscalculation. Or are you building on a greenfield site with no house within several kilometers and completely unknown ground conditions
 

WilderSueden

2022-08-03 08:54:23
  • #5
I suspect that originally a normal flat rate for earthworks was calculated and then the soil expert wanted the pile foundation. This is quite complex and expensive. Usually, the areas where this is necessary are known (in the industrial area here at the Seerhein, construction is only done with pile foundations), but as an outsider you can of course fall into the trap.
 

driver55

2022-08-03 19:04:55
  • #6
There was also the other post "Baugrundgutachten vor Grundstückskauf"...
 

Similar topics
01.12.2014Real estate transfer tax / what is the tax applied to? Which developer MUST?30
03.05.2015Financing with KFW, expert's signature14
22.12.2015KFW 70 funding still in 201524
02.08.2016Approximate ancillary construction costs - gap in financing10
10.09.2016Construction financing and contract with the developer24
26.10.2016Is this financing feasible?27
31.03.2018KfW financing - roughly estimated the following scenario10
02.07.2019Own contribution in financing a single-family house11
21.10.2019Financing with building savings loan + KfW + subordinated loan17
22.04.2020Single-family home financing through stocks39
01.07.2020Financing via KFW 55 or still from the bank?18
09.08.2020Bank does not accept own contribution206
23.04.2021Feasibility Single-family house - Cost statement / Financing realistic?126
09.09.2021KfW 261 if the developer has already applied for funding11
03.12.2021Financing a condominium: full repayment or not?29
08.12.2021Would you build yourself again or use a developer?31
16.03.2022Additional construction costs when building a house with a developer88
19.08.2022Fix financing early – no room for negotiation with the home builder?18
02.02.2025Construction financing as a young couple including own contribution20
02.06.2025House financing KfW 300 & 124 - please provide an assessment26

Oben