Zinada1
2022-08-02 10:25:16
- #1
Good day,
unfortunately, we need to refinance €30,000 for our construction project. Although we had planned a buffer when finalizing the financing, the costs for the earthworks have significantly exploded. Due to pile foundation, excavation, construction road, as well as the beam grid for the pile foundation + waterproof concrete slab, the costs amounted to nearly €100,000. We had planned €50,000 as a buffer, and we were able to save €20,000 in the last 8 months.
We have taken out 2 loans. 1. through an insurance company with a term of 36 years 2. €150,000 through the KFW.
Our bank advisor recommended that we arrange follow-up financing through the KFW. Now they want a cost breakdown from our developer including all additional costs. However, we assigned all the earthworks as own work, and our developer had nothing to do with it. The price of the house has not changed since the financing was finalized; only the earthworks caused additional costs.
How do I now correctly communicate this to the bank? Should I prepare a separate cost breakdown for the earthworks? Our developer does not want to sign for the own work.
unfortunately, we need to refinance €30,000 for our construction project. Although we had planned a buffer when finalizing the financing, the costs for the earthworks have significantly exploded. Due to pile foundation, excavation, construction road, as well as the beam grid for the pile foundation + waterproof concrete slab, the costs amounted to nearly €100,000. We had planned €50,000 as a buffer, and we were able to save €20,000 in the last 8 months.
We have taken out 2 loans. 1. through an insurance company with a term of 36 years 2. €150,000 through the KFW.
Our bank advisor recommended that we arrange follow-up financing through the KFW. Now they want a cost breakdown from our developer including all additional costs. However, we assigned all the earthworks as own work, and our developer had nothing to do with it. The price of the house has not changed since the financing was finalized; only the earthworks caused additional costs.
How do I now correctly communicate this to the bank? Should I prepare a separate cost breakdown for the earthworks? Our developer does not want to sign for the own work.