Shadowblues
2015-04-21 11:04:27
- #1
Hello everyone,
I am a bit puzzled right now and need your help. Here is the situation:
The house was completed last year with windows, etc., except for the exterior plaster. By February, the interior finishing and moving in were planned. Now the exterior plaster is supposed to be done (actually already in October, but the plasterer never had time).
I have painted the external roller shutters in RAL color, electric. These have 3mm metal sheets on the left and right, then comes the inspection flap. The way my plasterer has now installed the plastering beads, I would no longer be able to access the roller shutter box without chipping away the plaster. Of course, I have stopped that for now.
My plasterer now says that according to the standard, the window must be plastered at least 5mm because the roller shutter rails are on it, and these must also be plastered 5mm. However, I do not want to break out the roller shutter rails from the plaster in case of problems, and the roller shutter box must remain accessible.
I have also found a reference that external roller shutters are only allowed to be installed after plastering. Unfortunately, I cannot find this anywhere in such a way that I can present it to the architect. Do you have anything on this?
My architect has no opinion once again... *sigh*
Is there a way to save the situation? Eight weeks without roller shutters would be really bad - the children need it dark to sleep. Or do the things have to be removed? Or something completely different?
Regards Roger
I am a bit puzzled right now and need your help. Here is the situation:
The house was completed last year with windows, etc., except for the exterior plaster. By February, the interior finishing and moving in were planned. Now the exterior plaster is supposed to be done (actually already in October, but the plasterer never had time).
I have painted the external roller shutters in RAL color, electric. These have 3mm metal sheets on the left and right, then comes the inspection flap. The way my plasterer has now installed the plastering beads, I would no longer be able to access the roller shutter box without chipping away the plaster. Of course, I have stopped that for now.
My plasterer now says that according to the standard, the window must be plastered at least 5mm because the roller shutter rails are on it, and these must also be plastered 5mm. However, I do not want to break out the roller shutter rails from the plaster in case of problems, and the roller shutter box must remain accessible.
I have also found a reference that external roller shutters are only allowed to be installed after plastering. Unfortunately, I cannot find this anywhere in such a way that I can present it to the architect. Do you have anything on this?
My architect has no opinion once again... *sigh*
Is there a way to save the situation? Eight weeks without roller shutters would be really bad - the children need it dark to sleep. Or do the things have to be removed? Or something completely different?
Regards Roger