You need the electrician right at the beginning for the grounding before the foundation is poured! It must be done correctly and documented. He needs this for registering the house with the power supplier.
Hi there... we are also building through a developer and now we have the following problem... The grounding was not installed and checked according to the new regulations!
Before everything started, I was looking for an electrician myself instead of accepting the one from the developer straight away. Now the grounding (done by the shell builder) was fitted with the wrong clamps and no inspection was carried out by a specialist. So there is no documentation..? I am referring to the "DIN 18014-2014-03."
Later, a ring earth electrode is supposed to be installed.
The fact is... where do I get the documents? Am I to blame now?