Fragenasker
2020-11-16 06:01:58
- #1
Hello everyone,
let's assume someone is currently building a turnkey house, traditionally with a general contractor (GC), who in turn commissions individual subcontractors for the various trades.
In the contract signed in January 2020, it was agreed that the house construction sum would be paid in individual installments depending on the completion of the trades. So, for example, if the roof structure has been erected, installment 5 would be due, which might amount to 10% of the total sum. The house is to be accepted after completion.
Only painting and tiling work have been excluded as self-performed work from the overall contract. These are awarded by the builder to companies known to him.
Due to Christmas, the companies and the GC will only work until December 22, 2020.
As everyone knows, the VAT reduction (16%) applies only until December 31, 2020. The reduced 3% makes a significant amount in house construction.
The builder now faces the problem that the screed was laid on October 29, 2020, but the gas connection will only follow on November 23, so the underfloor heating can only be heated up starting November 24. Based on the heating program (a total of 17 days), painters and tilers could only start their work around December 12, 2020.
From November 12, 2020, the following work remains to be done:
- Painting work (self-performed)
- Tiling work (self-performed)
- Installation of sanitary fixtures (WC on the ground floor + bathroom upstairs) (GC)
- Installation of doors (GC)
- Installation of stairs (GC).
It is definitely not possible to complete all the work by December 22, 2020.
It seems possible that the WC on the ground floor can be tiled and that the sanitary fixtures and door can at least be installed there. This would make the house at least "ready for occupancy." In addition, the staircase will be installed.
Question:
Are there any helpful tips on how to still carry out the final acceptance on December 22, 2020, if some smaller services (all sanitary fixtures, all doors) are not yet completed?
Could, for example, the installation of the doors and remaining sanitary fixtures be agreed upon as remaining services in January 2021, with a first major final acceptance already taking place on December 22, 2020, in order to still receive the 16% VAT for all trades accepted up to that point?
I am grateful for all answers!
let's assume someone is currently building a turnkey house, traditionally with a general contractor (GC), who in turn commissions individual subcontractors for the various trades.
In the contract signed in January 2020, it was agreed that the house construction sum would be paid in individual installments depending on the completion of the trades. So, for example, if the roof structure has been erected, installment 5 would be due, which might amount to 10% of the total sum. The house is to be accepted after completion.
Only painting and tiling work have been excluded as self-performed work from the overall contract. These are awarded by the builder to companies known to him.
Due to Christmas, the companies and the GC will only work until December 22, 2020.
As everyone knows, the VAT reduction (16%) applies only until December 31, 2020. The reduced 3% makes a significant amount in house construction.
The builder now faces the problem that the screed was laid on October 29, 2020, but the gas connection will only follow on November 23, so the underfloor heating can only be heated up starting November 24. Based on the heating program (a total of 17 days), painters and tilers could only start their work around December 12, 2020.
From November 12, 2020, the following work remains to be done:
- Painting work (self-performed)
- Tiling work (self-performed)
- Installation of sanitary fixtures (WC on the ground floor + bathroom upstairs) (GC)
- Installation of doors (GC)
- Installation of stairs (GC).
It is definitely not possible to complete all the work by December 22, 2020.
It seems possible that the WC on the ground floor can be tiled and that the sanitary fixtures and door can at least be installed there. This would make the house at least "ready for occupancy." In addition, the staircase will be installed.
Question:
Are there any helpful tips on how to still carry out the final acceptance on December 22, 2020, if some smaller services (all sanitary fixtures, all doors) are not yet completed?
Could, for example, the installation of the doors and remaining sanitary fixtures be agreed upon as remaining services in January 2021, with a first major final acceptance already taking place on December 22, 2020, in order to still receive the 16% VAT for all trades accepted up to that point?
I am grateful for all answers!