2017-08-28 11:50:55
- #1
Hello,
we started building at the beginning of the year and the acceptance is now scheduled for October. So far, everything has been done with good quality, but I have noticed the following points that deviate from the plans and that the developer does not acknowledge:
1. On the street side, there are 6 windows that were supposed to be the same size and were planned as such on the plans. Now the upper windows are 14 cm longer than the lower ones.
2. From my daughters' bedrooms to the balcony, there is now a 16 cm high step that does not appear on any of the plans. It must be due to the slope on the balcony. Because of this, the balcony doors are also shorter than on the plans.
3. Due to the higher structure on the balcony, the parapet (masonry) also had to be raised. Because of this, this house view now deviates from the plan as well, since less of the patio doors are visible from the outside.
These changes were neither discussed with us beforehand nor approved by us.
Since we still have 65 sqm of tiles to be installed by the developer, I offered him that he could cover half of the costs and we would forget the points mentioned, but he declined.
How should we proceed? The house views do not match what we wanted and planned. Ultimately, we will have to live with it, but I do not see why we should pay for something we did not order. After all, the developer charges us heavily for every change we request. The developer himself admits no mistakes, everything is claimed to be normal...
we started building at the beginning of the year and the acceptance is now scheduled for October. So far, everything has been done with good quality, but I have noticed the following points that deviate from the plans and that the developer does not acknowledge:
1. On the street side, there are 6 windows that were supposed to be the same size and were planned as such on the plans. Now the upper windows are 14 cm longer than the lower ones.
2. From my daughters' bedrooms to the balcony, there is now a 16 cm high step that does not appear on any of the plans. It must be due to the slope on the balcony. Because of this, the balcony doors are also shorter than on the plans.
3. Due to the higher structure on the balcony, the parapet (masonry) also had to be raised. Because of this, this house view now deviates from the plan as well, since less of the patio doors are visible from the outside.
These changes were neither discussed with us beforehand nor approved by us.
Since we still have 65 sqm of tiles to be installed by the developer, I offered him that he could cover half of the costs and we would forget the points mentioned, but he declined.
How should we proceed? The house views do not match what we wanted and planned. Ultimately, we will have to live with it, but I do not see why we should pay for something we did not order. After all, the developer charges us heavily for every change we request. The developer himself admits no mistakes, everything is claimed to be normal...