Hello dear ones,

we have hired a construction company and have a fixed price guarantee for 12.5 months.
Now we are at the stage where we have submitted the plans to the district office for approval, and as it turns out, they want additional documents.
I have the impression that my construction company is dragging their feet because they are not delivering the missing documents right away, etc.
The current problem is that the height measurements have not been done, and now I have to find a surveyor. Shouldn’t something like that have been done before submitting the documents? Moreover, is that even my responsibility? Unfortunately, the contract says nothing about this, but I assumed the construction company would handle something like this. Why is this coming up now?
Honestly, I have the impression that this is being done intentionally so that we cannot keep the fixed price.
Can anyone explain this or does anyone have a tip on what I should do in this case? I am currently also considering consulting a lawyer.
Would be grateful for feedback.
Best regards Yasmin
 

WilderSueden

2022-07-04 18:43:06
  • #2
Hello Yasmin, if nothing about the surveyor is mentioned in your scope of services, then it is not included and the client has to organize and pay for it. What makes me suspicious here is that you have already submitted a building application. Who created it and based on which survey documents?
 

SoL

2022-07-04 18:47:03
  • #3
With us, surveying would also have had to be commissioned by the client side.

Did you have the construction service description (contract) checked or just signed it blindly?

What does it say, for example, about earthworks, site setup, construction power, construction water, etc.?
No offense, but if you have already overlooked the surveyor, now is definitely the time to read the contract very carefully again, otherwise the fixed price guarantee will surely be lost at some point because you thought something was included and the construction site is stuck.
 

ypg

2022-07-04 23:04:11
  • #4
Unfortunately, I can't say anything different either.

If nothing is stated in the construction service description, it is not included.
Then, I assume you have not had them checked, more items will come your way.

"Assuming" is not part of the contract's performance.
You can still have the contract reviewed afterwards. Costs a few hundred euros... then you will be sure regarding additional costs. The next big chunk "earthworks" is coming up!
 

Yaso2.0

2022-07-05 09:12:11
  • #5


Surveying has to be done, and everything that is not included as an inclusive service in the contract is probably always the responsibility of the client. So your task.

In our contract, this was also not included, but the construction company works with a surveyor. They commissioned him and we paid for it.

To protect your own interests, I would also act as quickly as possible.

However, one question is also bothering me, namely this one..



The documents for the building application must contain the exact position and height information.
 

SoL

2022-07-05 09:27:33
  • #6

As I understand it, the building application was submitted without position / height / ... and the office said "Half of it is missing! Please submit it later!"
 

Similar topics
16.05.2015Contract unclear: humus earth collectors10
04.07.2016Building without a contract - Concerns?39
28.09.2016Evaluation of earthworks offer14
01.12.2016Construction company rejects change requests in construction service description and construction contract39
28.05.2017Plundering the Riester contract - for less need for credit?16
28.08.2017Earthworks: Making the right choice of provider14
16.08.2018Civil engineering works without a contract - normal, experiences?10
29.10.2018Earthworks in the construction performance description17
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
09.05.2021Price adjustment clause in the contract with the general contractor18
11.06.2021Construction performance description from the favorite - Is something missing?65
23.07.2021Earthworks... Dispute with the occupational disability insurance20
15.03.2022Cost planning for earthworks33
30.03.2022Terminate the contract with the general contractor "early"22
10.08.2022Foundation cushioning Town & Country house construction service description10
16.08.2022Evaluation of Offer + Construction Description of New Bungalow29
06.09.2024Contractual penalty in the Building Code contract - new construction20
28.09.2024Architect commissions surveyor without the homeowner's consent.45

Oben