Surcharges of 10% despite a fixed price contract

  • Erstellt am 2022-03-28 22:46:55

Lioness

2022-03-29 10:10:08
  • #1
5% down payment after contract signing has already been made. No contractual penalties have been agreed upon.
 

gutentag

2022-03-29 10:20:27
  • #2
How high is the contract performance bond?
 

gutentag

2022-03-29 10:28:27
  • #3
What has the company done so far? What exactly does the company understand by the current situation? Germany is not at war, which could possibly justify a price change that the contractor does not have to bear. Corona was already 12 months ago, that is not an argument.
 

Lioness

2022-03-29 10:35:54
  • #4
We do not have a contract performance bond. The company has so far created the factory planning based on the architect's plans.
 

cryptoki

2022-03-29 10:39:16
  • #5
Is there a timeframe for completion or readiness for occupancy in the contract?
 

Lioness

2022-03-29 10:47:23
  • #6
it is only defined... completion after 8 months from the start of construction... since we were still enticed with the old KfW and Bafa subsidies at the time of contract signing, we assumed that our house would then be realized within the period of the approved subsidies, i.e. by February 2023 at the latest
 

Similar topics
16.02.2016Question about contractual completion14
03.09.2016Buy the kitchen more than a year before completion?54
08.08.2016Payment before or after completion of the construction phase?51
28.02.2017Are securities customary for completion and warranty?24
19.08.2018Strategically well-planned handover completion under building supervision11
19.07.2019Subsidies: how effective? And sensible when using own funds?23
29.09.2020Building permit before completion of development31
14.11.2021Sell an apartment from a two-family house immediately after completion34
14.04.2022Funding outside of KFW - What still makes sense now?54
01.07.2022Construction delay without completion. The house simply is not finished21

Oben