okay, the strip foundation, or in this case also the ring beam, was planned anyway. I just have some doubts about whether it is really necessary or simply oversized. After all, this is about a pool and not a residential building.
I will embed the steel directly into the foundation and not drill it in afterwards, that provides more stability. I might also make complete cages into the foundation and not just individual rods.
According to the manufacturer's load specifications, the 17.5 cm stones are sufficient for use under traffic load.
The ground will be concreted inside. So basically first the outer walls are erected and then inside gravel and a 10 cm floor slab with reinforcement. The floor slab would actually not be necessary since the pool will be lined with foil. A layer of compacted sand would have sufficed but when installing the foil there are impressions on the floor that cannot be smoothed out anymore, hence the 10 cm floor slab. I would have actually only made 5 cm but I am afraid it would break due to the pressure.
Once the floor slab is in, it can no longer come loose from anything.
Generally, it is natural soil and the subsoil is a heavily compacted clay soil and directly below that begins a rock layer.