Screed has been in for three days and is still wet?

  • Erstellt am 2023-07-23 13:44:39

WilderSueden

2023-07-25 15:11:31
  • #1
I first thought about not writing anything here, but otherwise the OP would be driven crazy. In the past, construction was done differently. Thumb-thick mortar joints between the rows of stones bring a few orders of magnitude more moisture into the masonry than the thin-bed mortar of today's times. Today, the moisture comes almost exclusively from the plaster and screed. However, 15 cubic meters is already estimated to be quite at the upper end if you look at my construction water consumption. And a large part is bound and does not go out. Nevertheless, a lot remains, especially in summer it is hard to ventilate away because the temperature difference is missing. The best thing is to put a few hygrometers in the house and observe them.
 

HeimatBauer

2023-07-26 07:31:15
  • #2
Were no moisture sensors embedded in the screed? In our case, a little flag was sticking out of the screed in every room, and the painter didn't touch anything until the value was right.
 

Bauherrin123

2023-07-26 08:02:51
  • #3


Screed is not a problem. Yesterday we were at the construction meeting, and the site manager said the screed must lie for 21 days until it is dry, and after 30 days it may be covered (laminate, tiles), but before that a test is done to check if it really is dry. CM testing?

So they seem to be exact about that. Now he said the drywall installer is coming already this week. Even though the attic is still wet. Both the floor and the film on the attic ceiling. After one week, in his opinion, it would be no problem, and the drywall installer knows exactly what he is doing. We rejected that and were able to postpone the drywall installer to Monday. We are supposed to make an appointment with him, but even Monday with 10 days is too early.

The problem is that three row houses are being built together, our screed was laid last. The neighbor is stressing all the time and wants to move in in August, and the construction company has been terrorized by him the whole time because of that. That’s why our site manager wanted to have the house connections installed and enter the house one day after our screed was laid. Otherwise, the city can only come for the connections two weeks later, which would be too late for the neighbor. I thought that was impossible and explicitly said that our front door would stay closed for 3 days. We were lucky that it didn’t work out with the city after all, and they will only come next week.

The same applies to the drywall installer. Yesterday the site manager said the drywall installer must come by Monday at the latest, even though everything is still so wet. The other two houses have been finished for a long time. Our screed took a bit longer to be laid, so the neighbors have had theirs lying down for 4 or 6 weeks, and the drywall installer is already done with both. I am pretty sure the reason the drywall installer is supposed to finish quickly with us now is that certain companies can then come who only come once for all the houses. And the neighbors don’t want to “wait” for us, and the site manager wants to do it quickly now so that the other houses can be finished. Unfortunately, I don't know much about it, so my question is, when is the drywall installer allowed to work?

I trust no one; both the site manager and the hired companies are in cahoots. Often I have acted according to my feeling and my mind, and that was always right. Nevertheless, at this point, I would like an expert opinion from you on what is right or what you would have done.

Thank you very much
 

Bauherrin123

2023-07-26 08:05:17
  • #4


Yes, we did. By the way, at some point the screed will also be heated for 10 days. Since the neighbor is complaining so loudly, he has already received a replacement heater, and his house is being heated until the proper ones arrive; these have been ordered.
 

mr.xyz1

2023-07-26 08:13:58
  • #5
We recently received our screed, and we have a 4-week drying phase followed by 3 weeks of heating.
 

Bauherrin123

2023-07-26 08:15:33
  • #6

And nothing is done in between? What kind of screed do you have? We have cement screed.
 

Similar topics
29.01.2014Cost saving/basement/affordable tiles/sealed screed?13
10.05.2015Screed uneven - defect removal refused52
13.04.2017Screed with gold sand17
28.04.2016Order screed - plaster14
07.08.2016Upper floor without screed - only concrete floor15
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
31.10.2016Heating the screed with the utility provider?!12
29.11.2016Front door only burglary protection / better materials - plaster, screed?10
02.02.2017Is ventilation/drying after installing screed/interior plaster sensible?15
11.02.2017Heating of screed ready for covering23
05.04.2017Super disaster - water pipe burst, screed damp31
30.04.2017Screed applied too high - room height consequently lower11
05.08.2017Screed necessary? Unfinished but insulated attic23
19.08.2017Technical room before installing screed: should the technology be painted now or later?16
05.11.2017Screed in the bathroom applied incorrectly - What to do?18
27.12.2017Underfloor heating heating demand with at least 60 mm screed30
31.01.2018Filling the screed at wall breakthrough - How to proceed correctly?10
07.10.2018Styrofoam under screed and underfloor heating - What is the name of the product?12
06.11.2018Recess in the screed 5 cm high - How is it done?10
10.02.2022Screed heating program incorrectly set and heating coil loosened18

Oben